'Predatory Pricing' Charge for Mitsubishi

PT LNG Energi Utama is demanding that Mitsubishi Corp., Japan's largest trading company, pay it upward of $709 million for potential losses from the Senoro-Matindok gas project in Central Sulawesi Province, after Mitsubishi allegedly manipulated confidential data to win the contract, Energi Utama lawyers said this week.

"We alleged that Mitsubishi used predatory pricing when it lowered the price from its real cost just to secure the project," said Rikrik Rizkiyana, an adviser for Energi Utama.

"It caused us to lose the bid, and we lost our revenue potential of around $709 million."

In May 2005, LNG International, the parent company of Energi Utama, obtained an six-month exclusive agreement with PT Pertamina and PT Medco Energi Internasional Tbk to develop the Senoro field. The company then began preparations, spending some $20 million on the site. It also formed Energi Utama at that time.

Pertamina and Medco invited Mitsubishi as a prospective investor. Mitsubishi, as part of the terms of the agreement, then performed due diligence on Energi Utama, according to Rikrik.

But Energi Utama later said that Mitsubishi stole confidential data from the company, which it alleges Mitsubishi used to calculate production costs and service fees to win the Senoro contract, Rikrik said. He also accused Mitsubishi of doubling the construction costs from $700 million to $1.8 billion.

In September 2006, an open tender for the project began and Energi Utama, along with Mitsubishi, was invited. Mitsubishi ultimately won the contract.

The site reportedly contains about 56 billion cubic meters of gas reserves.

After its win, Mitsubishi established PT Donggi Senoro LNG, of which Mitsubishi owned 51 percent, Medco 20 percent and Pertamina 29 percent. The consortium named Japan Gas Corp. as a main contractor.

The value of the project then rose to $1.8 billion in November, causing Pertamina and Medco to ask JGC to recalculate its costs. Operations were then delayed until 2012 from the field's original 2009 target.

In August, Energi Utama filed a lawsuit with the Business Competition Supervisory Commission, or KPPU, asking it to cancel Mitsubishi's contract. The company argued that Mitsubishi violated Indonesian business competition laws.

"The case is currently undergoing a clarification process and is expected to go to trial in March 2009," Rikrik said. If Energi Utama wins, Mitsubishi would have to compensate Energi Utama and withdraw from the project.

Budi Basuki, president director of Medco's production unit, said the case involved an exclusivity agreement between Pertamina, Medco and Energy Utama to construct and buy gas from the project.

He said, however, that the agreement was only temporary and had expired.

"Since then, Pertamina and Medco have created a new scheme for the project without involving Energi Utama," he said.

Anang Rizkani Noor, Pertamina's vice president for public relations, said the company was waiting to see how the issue developed, adding only that "Mitsubishi has been chosen through a fair bidding process."

Energy expert Widjajono Partowidagdo noted that "Pertamina had a good, long-term relationship with Japan" as an LNG buyer, and "therefore they usually are more comfortable working with Mitsubishi," especially given that the Japan Bank for International Cooperation helped finance the project.

Jakarta Globe

More from 5 December 2008 โ†’

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/indonesias-pt-lng-energi-utama-charges-mitsubishi-corp-for-predatory-pricing-1228410000)
Originally published by The Jakarta Globe
Print