WIKAIKON Installs Steel Box Girders Weighing Up to 240 Tonnes on Serang–Panimbang Toll Road Section 3
Image: Antara (Indonesian)

Jakarta (ANTARA) – PT Wijaya Karya Industri & Konstruksi (WIKAIKON), a subsidiary of PT Wijaya Karya (Persero) Tbk (WIKA), is undertaking the fabrication and installation of steel box girders for Phase 2, Package 1 of the Serang–Panimbang Toll Road Section 3 (Cileles–Panimbang) construction project. In line with the third Asta Cita priority of continuing infrastructure development, the toll road is expected to improve public mobility and goods distribution, as well as provide access to industrial areas and tourist destinations in southern Banten.

WIKAIKON is carrying out the work as an integrated process, from fabrication and transport to assembly and installation at the project site. The structure comprises four spans, each 70 metres long, with six girder lines on each span. In total, there are 24 girder lines made up of 168 segments, with the heaviest girder weighing up to 240 tonnes.

All components are manufactured at WIKAIKON’s steel fabrication plant in Majalengka, West Java, which has a capacity of up to 65,000 tonnes of steel a year. Each component undergoes quality inspections to ensure the materials, dimensions, joints and structural form meet project specifications.

WIKAIKON President Director Tri Prabowo said the company’s involvement in the project reflects its ability to handle highly complex steel-structure work. “The steel box girder work on the Serang–Panimbang Toll Road project is one example of WIKAIKON’s ability to provide integrated steel-structure solutions, from fabrication through to installation in the field,” Tri said.

After fabrication, the components are transported to the project site for assembly before installation. Because of their size and weight, the girders are moved using special multi-axle transport vehicles, then lifted and positioned using cranes with capacities of 450 tonnes and 500 tonnes.

Before lifting, the WIKAIKON team checks the readiness of the structure and lifting equipment, the transport route and the work area to ensure that installation is safe and precise. WIKAIKON also applies quality, environmental and occupational health and safety management systems that meet ISO 9001, ISO 14001 and ISO 45001 standards, as well as the occupational safety management system set out under Government Regulation No. 50 of 2012.

“With production facilities, engineering expertise, equipment readiness, and the application of quality and workplace safety standards, we are committed to delivering high-quality, precise work that meets the project’s needs,” Tri Prabowo concluded.

More from 3 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/wikaikon-installs-steel-box-girders-weighing-up-to-240-tonnes-on-serang-panimbang-toll-road-section-3-1793710441)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5829451/wikaikon-pasang-steel-box-girder-hingga-240-ton-di-tol-serang-panimbang-seksi-3), translated from Indonesian
Print