WIKA Optimises Completion of Sekolah Rakyat Banyumas Ahead of June 2026 Target

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
WIKA Optimises Completion of Sekolah Rakyat Banyumas Ahead of June 2026 Target
Image: Antara (Indonesian)

Jakarta (ANTARA) - PT Wijaya Karya (Persero) Tbk (WIKA) continues to accelerate the construction of Sekolah Rakyat Banyumas as part of the government’s programme to widen access to education that is equitable and of high quality for the community.

As of 19 May 2026, the construction progress of Sekolah Rakyat Banyumas had reached 65.58% and is targeted for completion on 20 June 2026. Currently, on-site work includes finishing works, roof tiling installation, mechanical, electrical, and plumbing (MEP) works, as well as infrastructure and landscape works.

To support accelerated project completion, WIKA has implemented a number of strategies, one of which is changing the wall construction method by using precast materials. In addition, WIKA is expediting the procurement and delivery of finishing materials and MEP components, increasing the workforce, and implementing a 24-hour operation with two shifts. The working hours are from 08:00–22:00 WIB and 19:00–06:00 WIB.

The project is currently supported by 1,011 workers. In addition, most major materials have been delivered and placed in a temporary warehouse located near the project area to ensure smooth distribution and on-site execution of works.

Corporate Secretary Ngatemin of PT Wijaya Karya (Persero) Tbk said that WIKA continues to optimise all resources to ensure Sekolah Rakyat Banyumas can be completed on target, while maintaining the quality of work and safety on site.

“WIKA continues to accelerate the construction of Sekolah Rakyat Banyumas through optimising labour, expediting materials, implementing a 24-hour system, and adjusting wall construction methods using precast materials so that the project can be completed on target. In the face of challenges such as design changes and weather conditions dominated by rain, WIKA remains committed to ensuring all stages of work proceed in accordance with quality and safety standards through the implementation of safety and quality induction, Safety Morning Talk (SMT), daily Tool Box Meetings (TBM), and by adding quality and HSE personnel on site,” Ngatemin said.

Ngatemin added that the construction of Sekolah Rakyat Banyumas is expected to bring tangible benefits to the community, particularly in supporting equitable access to quality education and in developing Indonesia’s high-calibre human resources.

In its implementation, WIKA also continues to strengthen the supervision of work quality and the implementation of Health, Safety, and Environment (HSE) aspects from the outset of the project to ensure all construction processes run safely, orderly, and in accordance with the company’s standards.

With these acceleration efforts, WIKA is confident that the Sekolah Rakyat Banyumas project can be completed on time and soon utilised by the community as an educational facility that supports the improvement of Indonesia’s human resources.

More from 20 May 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/wika-optimises-completion-of-sekolah-rakyat-banyumas-ahead-of-june-2026-target-1779545617)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5575029/wika-optimalkan-penyelesaian-sekolah-rakyat-banyumas-jelang-target-juni-2026), translated from Indonesian
Print