WIKA Continues Jogja-Bawen Toll Road Section 3, Targeting Completion by June 2028
PT Wijaya Karya (Persero) Tbk (WIKA), as part of the KSO PP-Waskita-WIKA consortium, is continuing the construction of Section 3 of the Jogja-Bawen Toll Road, with a target completion date of June 2028.
This toll road is a vital component of the connectivity linking the Yogyakarta and Central Java regions, while simultaneously strengthening the strategic Joglosemar (Yogyakarta-Solo-Semarang) corridor. The infrastructure is intended to support access to the Borobudur area and stimulate public mobility and economic activity in the surrounding regions.
WIKA Corporate Secretary Ngatemin stated that the development of Section 3 of the Jogja-Bawen Toll Road is expected to not only strengthen inter-regional connectivity but also provide sustainable benefits for the community and the Borobudur region.
“Our hope is that the construction of the Jogja-Bawen Toll Road Section 3 can provide long-term benefits for the public, particularly in improving connectivity and mobility, and facilitating tourist access to the Borobudur area, which will ultimately support the economy of the Magelang community,” Ngatemin said in a written statement on Monday (5/10/2026).
Furthermore, Ngatemin noted that this infrastructure development must proceed in tandem with environmental and cultural preservation, as well as the interests of local communities, ensuring that the resulting infrastructure is both high-quality and sustainable.
Currently, work on Section 3 is in the earthworks stage, which includes excavation, the construction of box culverts and traffic boxes, and bore piling for bridge structures. Work acceleration is focused on completing excavations, embankments, and structures through daily and weekly productivity monitoring and the management of critical path tasks.
As part of the connectivity efforts towards the Borobudur area, the construction of Section 3 aligns with the ‘Asta Cita’ programme, specifically in promoting infrastructure development that supports connectivity and tourism while respecting environmental sustainability and cultural preservation.
Because the project site borders the Borobudur area, environmental and cultural aspects are primary considerations during construction. Mitigation measures include controlling work methods, heavy machinery movement, dust, vibration, and noise, as well as managing materials and waste in accordance with the regulations of the project owner and relevant authorities. This approach is implemented to minimise disturbances to the environment and the cultural sites surrounding the project.
For several structural works, including pile slabs, controls are being implemented more strictly due to the active condition of the national road, soil conditions, and groundwater levels.
Controls include the verification of geotechnical data, selection of construction methods, monitoring of deformation and elevation, traffic management during works, and quality inspections regarding point accuracy, reinforcement, joints, pouring, and concrete test results.
The project also creates opportunities for the involvement of local labour, suppliers, and businesses in Magelang that meet the requirements for competence, quality, safety, and procurement regulations. This involvement is expected to provide added value and stimulate economic circulation for the communities around the project.
To support effective execution, WIKA is implementing several innovations, including the use of survey technology, data-based progress control, optimisation of equipment usage, and prefabrication.
Quality control is conducted from the planning stage through Inspection and Test Plans (ITP), checklists, and hold points to ensure work meets standards and to minimise the potential for rework. Excavated materials are also repurposed as embankment material in accordance with technical requirements, thereby increasing efficiency and reducing the mobilisation of heavy machinery and its resulting emissions.