WIKA Accelerates Semarang–Demak Toll Road Section 1B to Boost Pantura Connectivity and Mitigate Coastal Flooding
Jakarta (ANTARA) - PT Wijaya Karya (Persero) Tbk (WIKA) is continuing to accelerate the construction of the Semarang–Demak Toll Road Section 1B as part of efforts to strengthen connectivity in the North Coast of Java (Pantura) and support the integration of the Trans-Java Toll Road network. As of June 2026, the project’s construction progress has reached 81.19%, with completion targeted for April 2027.
For the Semarang–Demak Toll Road Section 1B project, WIKA’s scope of work includes Ramp On, Ramp Off, Main Road, sea dikes, combi walls, and revetments. Several major works have been completed, including the Ramp On, Ramp Off, Main Bridge, and Combi Wall. Meanwhile, ongoing work involves the placement of selected material top layers used as preloading for the sea dike.
The presence of the Semarang–Demak Toll Road plays a strategic role in reducing traffic congestion on the Pantura route, particularly on the Semarang–Demage section, and strengthening connectivity within the Trans-Java Toll Road system. In addition to supporting smooth public mobility and logistics distribution, the project is designed with a dual function as a sea dike.
This dual function is one of the key values of the project. Beyond being transport infrastructure, the Semarang–Demak Toll Road Section 1B is also part of a strategy to mitigate tidal flooding (rob) in the Semarang coastal area and its surroundings. The project is designed to help address tidal inundation, the impacts of land subsidence, and damage to the Pantura road caused by seawater flooding.
WIKA Corporate Secretary, Ngatemin, stated that the construction of the Semarang–Demak Toll Road Section 1B reflects WIKA’s contribution to providing infrastructure that is not only oriented towards connectivity but also provides direct benefits to coastal communities.
“The Semarang–Demak Toll Road Section 1B is a strategic project with dual benefits, serving as both a primary connectivity route in Pantura and as tidal flood control infrastructure. Through this project, WIKA is committed to supporting infrastructure development that can meet mobility needs while providing protection for the Semarang coastal area,” he said.
In its implementation, the project faces significant construction challenges due to being built on soft soil and directly interacting with marine areas. To address these challenges, WIKA is applying specialised construction methods, including the use of bamboo piles and bamboo mats before placing embankment material on top. These bamboo structures function to maintain the stability of the embankment on soft soil while distributing the load evenly.
Furthermore, the project utilises Prefabricated Vertical Drain (PVD) technology for soil improvement. The embankment work is carried out in stages, observing waiting periods for each stage: 55 days for stages 1 through 5, and 150 days for stage 6. These stages are necessary to ensure that the embankment density meets the specified design requirements.
Regarding tidal flood control, the project is built with a sea dike elevation that sits above the highest sea level, equipped with revetment structures on the seaward side. The sea dike also works in synergy with retention basins designed to help control water levels on the landward side. Consequently, when sea levels rise, the land areas in coastal Semarang are expected to be protected from tidal flooding.
The construction of the Semarang–Demak Toll Road Section 1B also provides a positive impact on employment. During the peak of the bamboo mat work, the number of workers involved reached approximately 750, with about 200 being local residents. Local labour was particularly essential for the manual assembly of bamboo mats using nylon rope bindings.
Once fully operational, the Semarang–Demak Toll Road Section 1B is expected to provide long-term benefits to the community, particularly in easing traffic congestion on the Semarang–Terboyo–Demak Pantura route. Additionally, the sea dike component of this project is expected to help resolve tidal flooding issues in the Semarang coastal area, ensuring the benefits of the development are felt directly by the local population.