West Sumatra Kajati Praises Andre Rosiade for Initiating Bukittinggi-Sicincin Toll Road Project
The Chief Prosecutor of West Sumatra, Dedie Tri Haryadi, has given special recognition to Deputy Chairman of the Indonesian House of Representatives’ Commission VI, Andre Rosiade. The appreciation was for his role in initiating the construction of the Pekanbaru-Padang Toll Road’s Bukittinggi-Sicincin section.
Dedie made the statement after chairing a meeting on the preparation of toll road construction at the West Sumatra Prosecutor’s Office on Tuesday (14/7/2026).
The meeting was attended by all stakeholders, from regional government, the National Land Agency (BPN), the Ministry of Public Works, PT Hutama Karya, BPJN West Sumatra, to prosecutors’ officials.
“Today we discussed the Padang-Sicincin-Bukittinggi toll road. All stakeholders were present. In essence, the construction of this toll road is, God willing, ready to begin on time and on target, so that it can benefit the people of West Sumatra,” Dedie said.
In particular, Dedie expressed his appreciation to Andre Rosiade, who was regarded as the driving force behind the acceleration of this national strategic project.
“We are sincerely grateful to Mr Andre Rosiade. He initiated the construction of the toll road from Sicincin to Bukittinggi. The people of West Sumatra must also be grateful because this project will bring enormous benefits to the region,” Dedie said.
Dedie stressed that various issues that had previously hindered the construction have now been discussed and resolved through cross-agency coordination. All parties are now working as one solid team to ensure the project proceeds without obstacles.
“We have untangled them. We are one team, with solid and complete teamwork. The BPN together with the Head of the State Administration Section will go directly to the field to ensure the land status is truly clear and clean,” he said.
Regarding land acquisition, Dedie stated that the approach taken would strongly prioritise the interests of local communities.
“As Mr Andre said, this is not compensation for loss, but compensation for gain,” he remarked.
The West Sumatra Prosecutor’s Office has also committed to providing legal assistance should any problems arise in the future, including disputes involving customary (adat) communities.
“We will provide assistance if there are disputes involving customary communities. We will resolve them later,” he affirmed.
In response to the recognition, Andre Rosiade instead expressed his gratitude to the West Sumatra Chief Prosecutor and his entire staff, who he regarded as the main drivers behind the coordination to accelerate the toll road’s construction.
“As members of the House of Representatives, on behalf of all the people of West Sumatra, we thank the Chief Prosecutor and all staff of the West Sumatra High Prosecutor’s Office who have worked extraordinarily hard to initiate and coordinate this meeting. This is the third meeting, and, thank God, all the issues could be resolved,” Andre said.
Andre revealed that two main issues of concern had finally received concrete solutions. First, the toll route is confirmed to no longer pass through the Kubang Putih area in Agam Regency. Second, the location of the Padang Panjang toll exit has also been agreed with a new design closer to Bukittinggi City.
“The Kubang Putih issue is settled. The new route does not pass through Kubang Putih. I ask that the polemic be stopped immediately because all stakeholders have agreed. Likewise, the Tarasan Panjang toll exit has a new solution that is unproblematic,” said the Chairman of the Ikatan Keluarga Minang (IKM) Central Board.
According to Andre, the route change was made so that construction would not be continually delayed due to polemics in the field. He reminded that the interests of this toll project are far greater, as it will boost West Sumatra’s economic growth.
“If Padang is connected to Pekanbaru, West Sumatra’s agricultural produce can be shipped more easily to Riau. Conversely, the people of Riau can come to West Sumatra for weekend tourism. The economic turnover could reach hundreds of billions of rupiah per day. So this is not just for one village, but for the interests of all the people of West Sumatra,” he said.
With these issues mitigated, Andre is optimistic that PT Hutama Karya can begin construction of the Bukittinggi-Sicincin section by the end of this year.
Source: jawawa.id (https://jawawa.id/newsitem/west-sumatra-kajati-praises-andre-rosiade-for-initiating-bukittinggi-sicincin-toll-road-project-1784015672)
Originally published by detikcom (https://news.detik.com/berita/d-8573488/kajati-sumbar-puji-andre-rosiade-inisiasi-proyek-tol-bukittinggi-sicincin), translated from Indonesian