Lampung Timur (ANTARA) — The Joint Committee for the Mitigation and Handling of Negative Interactions with Sumatran Elephants in Way Kambas National Park (TNWK) has urged project contractor PT Puncak Mandala Indonesia (PMI) to repair immediately a section of protective embankment that collapsed in Braja Kencana village, Braja Selebah sub-district, East Lampung regency.

The request was made in a warning letter seeking clarification from PT PMI after about 30 metres of the embankment collapsed on 25 November 2026.

Sriyanto, chairman of the joint committee, said in East Lampung on Saturday that the incident was a serious concern because it involved the quality of the work and the structural safety of the protective embankment.

“This situation requires special attention to ensure the quality of the work and the safety of the construction, and to prevent similar damage in the future,” he said.

He said PT PMI had previously submitted a letter of guarantee and a statement undertaking to carry out maintenance for one year, signed by the company’s director, Fajar Iqbal.

The committee has therefore asked the contractor to honour that commitment by repairing and maintaining all embankment works in accordance with the agreed terms.

Under the warning letter, PT PMI is also required to submit a written explanation and six supporting documents no later than seven working days after receiving the letter.

Sriyanto said the committee would conduct a further review and consider administrative sanctions if the contractor failed to provide the requested clarification and documents by the deadline.

“We emphasise that if PT PMI has not submitted a response and the requested supporting documents by the specified deadline, the committee will conduct a further review and consider administrative measures in accordance with the applicable rules, the agreement documents and the maintenance commitment already agreed,” he said.

The committee hopes the embankment repairs will meet technical standards and the contractor’s commitments, so that the protective function of the TNWK area is maintained.

More from 28 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/way-kambas-elephant-mitigation-committee-urges-contractor-to-repair-collapsed-embankment-1795837940)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5884459/komite-mitigasi-gajah-tnwk-minta-kontraktor-perbaiki-tanggul-longsor), translated from Indonesian
Print