Several areas in South Kuta, Badung, Bali, have experienced water outages lasting up to a week. This supply disruption was caused by damage to the main pump motor, with repairs delayed because pump components were held up in transit from Java.

Viola, a resident of Kampial, reported that the water supply at her boarding house has been cut off for two consecutive days. She noted that residents in other areas have been facing disruptions for as long as a week.

“Several areas, such as Kampial, Kutuh, and Taman Griya, have already lost water. Some have even been without it for a week,” she stated when confirmed on Tuesday (29/09/2026).

To meet their water needs, Viola’s boarding house has been forced to purchase water to replenish their storage tanks.

“We live in a residential area; for example, one tank holds several thousand litres, so we have to share it with other houses,” she added.

Meanwhile, the President Director of Perumda Air Minumn Tirta Mangutama Badung Regency, I Wayan Suyasa, stated that the increased demand for water during the prolonged dry season is a contributing factor to the supply disruption.

“Currently, water demand is increasing due to the long drought. On the other hand, our raw water supply is also facing issues. Because of this prolonged dry season, raw water levels are somewhat low,” he explained when contacted.

The affected areas include Bualu Village, Sawangan Village, the Kampial area, Kutuh Village, Ungasan Village, Pecatu Village, the Labuan Sait area, the Balangan area, Jimbaran Village, and surrounding localities.

In addition to raw water issues, the disruption was caused by damage to the main pump engine. Suyasa explained that a short circuit occurred in the 800-kilowatt pump motor used to distribute water to South Badung from the Estuary Water Treatment Plant (IPA).

“We had a problem at our processing plant yesterday. One of our large pumps, located at the main station, experienced a short circuit. Because the pump is large, it requires more time for resolution,” he said.

Repairs to the pump were originally targeted for completion by Saturday (26/09/2026). However, the work was delayed because the engine had to undergo servicing in Semarang, Central Java. Once the repair process was complete, the pump components were shipped back to Badung.

During the journey to Bali, the shipment of components was delayed at Ketapang Port. The components only arrived in Badung on Tuesday afternoon (29/09/2026). This situation subsequently delayed the installation and repair process.

“Yesterday towards the afternoon, we were waiting for it at Ketapang. It only arrived here today, in the afternoon. Let’s say it arrived around 3:00 or 5:00 PM. This journey was a cause for our delay in execution,” he added.

Currently, two pumps with a capacity of 200 kilowatts each are operating with a flow of approximately 348 litres per second. Perumda Tirta Mangutama is also in the process of installing another 200-kilowatt pump motor to increase the flow rate by about 100 litres per second.

In addition to repairing the pumping system, Perumda Tirta Mangutama is distributing water using 5,000-litre water trucks to several points, including Kampial, Melangkaja, and Goa Gong Ungasan. Residents can collect water for free at the provided locations.

“We hope they use the collection points. It is free. We are also working to accelerate the process, both for the pumps and other aspects like piping, with the goal of faster execution,” he explained.

To support water distribution, Perumda Tirta Mangutama has prepared four tanker trucks and has also requested assistance from the Red Cross (PMI) and the Indonesian National Armed Forces (TNI). Suyasa confirmed that the installation of the pump motor is underway and is targeted for completion tonight.

“Work is currently in progress. It has arrived. We target completion by tonight,” he concluded.

More from 29 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/water-outage-lasts-a-week-in-south-kuta-the-root-cause-identified-1790693512)
Originally published by detikBali (https://www.detik.com/bali/berita/d-8685057/air-mati-sepekan-di-kuta-selatan-ini-biang-keroknya), translated from Indonesian
Print