Water Infrastructure in Padang City Reaches 92% Recovery, Kuranji-Maransi Projects Accelerated
The recovery of water resource infrastructure following disasters in Padang City, West Sumatra, has reached approximately 92 per cent. Subsequent efforts are focused on the Batang Kuranji-Maransi area to restore river functions while strengthening community protection against recurring flood risks.
Handling during this emergency response period includes dredging sedimentation, restoring river flows, and flood control works at several affected points. Physical works are now continuing through a transition period lasting until December 2026.
The Sumatra V River Basin Organisation (BWS Sumatera V) noted that there are 43 intervention points across West Sumatra. For the rehabilitation and reconstruction phase, 56 packages have been proposed, with 16 packages already under contract and 40 packages still undergoing the procurement process.
Permanent physical works are targeted to begin contracting by November 2026. However, implementation still faces several obstacles, particularly regarding design finalisation, the tender process, land acquisition, and the division of handling authorities.
In Batang Kuranji, dredging sedimentation in the downstream section has entered the implementation stage using the regular budget of BWS Sumatera V. Handling also needs to be extended to the upstream section through the construction of sediment control infrastructure to reduce material carried into the river flow.
“Batang Kuranji requires sedimentation normalisation and Sabo Dam handling in the upstream section,” stated Brigadier General Pol Yopie Indra Prasetyo Sepang, Chairman of the Monitoring and Evaluation Team of the National PRR Task Force, in his report on Saturday (19/09/2026).
The West Sumatra Provincial Government has supported the Batang Kuranji handling through an additional Regional Transfer of approximately Rp4 billion. This support still needs to be strengthened, as the total requirement for the area’s handling is estimated to reach Rp86 billion.
In addition to Batang Kuranji, the need for handling Batang Guo, Batang Maransi, Banda Luruh, and the Air Pacah-Maransi retention pond will be proposed through the updated Post-Disaster Rehabilitation and Reconstruction Plan. The estimated requirement for handling the Maransi-Air Pacah area and its surroundings is approximately Rp998 billion.
This update will also accommodate the impact of the floods on 3 August 202 and6. The Padang City Government, together with BWS Sumatera V, needs to prepare supporting data and evidence linking this event to the series of disaster impacts from late November 2025, so that the proposal can be discussed in the updated Master Plan in October 2026.
Besides flood control, the readiness of permanent housing (huntap) in Balai Gadang is also a priority. A total of 340 units of permanent housing provided by the Buddha Tzu Chi Foundation are planned to be built in two stages, consisting of 138 units in 2026 and 202 units in the following stage.
The construction of the additional 202 units still requires budget support for land maturation as well as infrastructure, facilities, and utilities. These requirements will be proposed in the updated R3P and Renduk.
As for the independent permanent housing scheme, BNPB has approved assistance for 23 housing units, and the local government has proposed an additional six units, bringing the total to 29 units. Currently, one house has been completed and has been occupied by a recipient for two months.
Source: jawawa.id (https://jawawa.id/newsitem/water-infrastructure-in-padang-city-reaches-92-recovery-kuranji-maransi-projects-accelerated-1789811678)
Originally published by detikcom (https://news.detik.com/berita/d-8670085/infrastruktur-air-di-kota-padang-pulih-92-kuranji-maransi-masih-dikebut), translated from Indonesian