Waskita Completes Jakarta LRT Phase 1B, Now Entering Trial Stage

| | Source: Republika Translated from Indonesian | Infrastructure
Waskita Completes Jakarta LRT Phase 1B, Now Entering Trial Stage
Image: Republika

The Jakarta Light Rail Transit (LRT) Phase 1B, constructed by PT Waskita Karya (Persero) Tbk, has entered a new chapter. The first operational and service trials were conducted on Thursday (10/09/2026). Waskita Karya’s Director of Operations II, Paulus Budi Kartiko, stated that this trial is part of an effort to introduce modern rail-based public transport services to the public, allowing them to experience the Jakarta LRT route from Kelapa Grending to Manggarai directly. However, he noted that further operational schedules have yet to be determined, as Jakpro, the project owner, will establish the upcoming schedule.

“In previous statements, we informed regarding a limited operational schedule. However, at this time, that information remains dynamic and uncertain, as we are awaiting the overall results of the trials,” explained Paulus in a written statement in Jakarta on Friday (11/09/2026).

Nevertheless, he emphasised that all construction stages of the Rp4.1 trillion project have been completed. Paulus also ensured that Jakarta LRT Phase 1B is safe and comfortable to use, having passed various thorough and structured testing sequences.

“We are grateful that the public can soon directly experience the Jakarta LRT Phase 1B facilities that we have built with great precision and calculation to provide the best experience for passengers. We believe that every metre of the LRT track is part of Waskita Karya’s responsibility as a contractor,” he said.

During the construction process, he continued, the Company always prioritised the implementation of Occupational Health and Safety (K3) standards on-site. This consistency is reflected in the achievement of 7.5 million safe man-hours without lost time injury during the Jakarta LRT 1B works.

“This achievement serves as an important foundation for executing a project situated amidst Jakarta’s heavy traffic and limited spaces, such as the construction of Jakarta LRT Phase 1B. This also strengthens our track record as a State-Owned Construction Enterprise with over 65 years of experience building various infrastructures,” said Paulus.

He noted that the Company built a 6.4-kilometre Jakarta LRT track equipped with five stations covering Rawamangun, Pramuka, Matraman, Proklamasi, and Manggarai. All stations in Jakarta are designed to be integrated with other forms of public transport.

“We believe that the presence of the LRT will not only support urban modernisation and connectivity but also have a positive impact on the environment. The use of public transport can reduce carbon emissions, thereby supporting the government’s Net Zero Emission (NZE) targets,” said Paulus.

As information, the trials conducted also involved various groups of participants from the media and creators, including print and electronic media, out-of-home media, online media, Key Opinion Leaders (KOL), and content creators. Their involvement is expected to provide a direct overview of the operational readiness and service quality of the Jakarta LRT to the public.

Each journey serves the route from Kelapa Gading Station to Manggarai Station and back to Kelapa Gading Station. During the trial period, the Jakarta LRT operates at a maximum speed of 40 kilometres per hour with a maximum service capacity of 100 passengers.

The President Director of Jakarta Propertindo (Jakpro), Iwan Takwin, stated that this trial not only provides direct experience to the public but also ensures comprehensive service readiness, regarding human resources (people), service processes (process), as well as supporting facilities and infrastructure (facility). At the same time, this activity serves as a momentum to build public awareness and engagement regarding the benefits of increasingly integrated public transport connectivity in Jakarta.

“The implementation is carried out in stages, in a measurable manner, and through continuous evaluation,” said Iwan.

Iwan stated that every stage is part of a validation and refinement process, ranging from journey testing and increasing service capacity to optimising train waiting times. He noted that the entire process is supported by monitoring the readiness of systems, facilities, and personnel.

“This step is part of the preparation to ensure that the Jakarta LRT can provide safe, comfortable, and reliable services when entering the full operational stage,” said Iwan.

More from 11 September 2026 →

Cite this article