Vice President Gibran Rakabuming has confirmed that the construction of the Keramasan Waste-to-Energy (PSEL) facility in Palembang, South Sumatra, is progressing according to target as part of efforts to strengthen environmental management and clean energy utilisation.

According to a statement from the Vice Presidential Secretariat received in Jakarta on Friday, Vice President Gibran conducted an inspection of the Keramasan PSEL on Thursday to ensure the strategic project remains on schedule.

“Going forward, the priority is to eliminate and reduce waste on a massive scale,” said Operational Manager of PSEL Keramasan, Satriawan Kirana, during a briefing to the Vice President.

He added that 1,000 tonnes of waste from Palembang can be processed into 17.7 megawatts of green energy. This clean electricity will subsequently be fed into Palembang’s main grid, meaning the waste produced by residents will return to them in the form of power supply.

The facility uses a moving grate incinerator, a type of furnace with a mechanically moving floor of grates. This grate shifts, turns, and tumbles the waste slowly to ensure complete combustion while moving it from the intake zone to the ash disposal zone.

During the dialogue, the Vice President also inquired about the management of ash generated from the processing. Responding to this, Satriawan explained that the ash will undergo a special treatment process so that it is no longer classified as hazardous and toxic waste (B3), but can instead be reused for various purposes.

He added that the combustion ash can be utilised as construction material, such as for reclamation fill or paving blocks. This residue utilisation is expected not only to reduce waste but also to create added value within a more efficient and sustainable waste management system.

Based on a report from the construction management and supervision consultant as of 30 June 2026, the physical construction progress of the Keramasan PSEL has reached 89.16 percent. The strategic facility is targeted for completion in October 2026.

Once operational, the Keramasan PSEL is expected to serve as a solution for urban waste management by significantly reducing waste volume while simultaneously generating environmentally friendly electricity.

More from 17 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/vice-president-confirms-keramasan-waste-to-energy-plant-on-track-for-october-2026-completion-1784260407)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5653368/wapres-pastikan-pembangunan-psel-keramasan-berjalan-sesuai-target), translated from Indonesian
Print