Vale Base Metals to Proceed with Coarse Particle Flotation at Salobo to Boost Copper Production

| Source: Antara (Indonesian) Translated from Indonesian | Mining
Vale Base Metals to Proceed with Coarse Particle Flotation at Salobo to Boost Copper Production
Image: Antara (Indonesian)

Coarse Particle Flotation (CPF) is expected to deliver additional copper production of up to approximately 30,000 tonnes per year and additional ore processing capacity of 6 million tonnes per year at Salobo. The initial phase of project operations has been accelerated to the first half of 2028, with construction permits already obtained. The estimated capital expenditure for CPF has been optimised, and Wheaton Precious Metals will fund $40 million of that expenditure. All figures are stated in US dollars unless otherwise indicated.

Vale Base Metals, a leading global supplier of critical minerals, announced that it will proceed with the Coarse Particle Flotation Project at the Salobo Copper Complex in Brazil, which will bring a significant increase in processing and production capacity and offer highly attractive project economics. The company expects the project to begin operations in the first half of 2028, approximately one year earlier than originally projected. This reinforces VBM’s optimised construction strategy and restructured project approach across the company, enabling it to move more nimbly, improve execution capability, and deliver industry-leading returns from its project portfolio and mineral resource base.

With this project, the annual ore processing capacity of the Salobo plant is expected to increase by 6 million tonnes to a total of 42 million tonnes per year. Annual copper production is projected to increase by up to approximately 30,000 tonnes of copper in concentrate, with an additional approximately 15,000 ounces of gold as a by-product, further strengthening Salobo’s production performance after record results in 2024 and 2025.

“The CPF project once again demonstrates VBM’s strength: our ability to unlock significant value and growth potential from world-class assets through effective execution, innovation, and disciplined capital allocation,” said Shaun Usmar, CEO of VBM. “Salobo is one of the world’s premier copper operations, and this project will allow us to increase copper production more efficiently by leveraging existing infrastructure while improving environmental performance.”

Usmar added: “While our industry continues to face challenges in delivering new copper supply, VBM is able to bring its copper expansion projects to fruition ahead of schedule. At the end of July, we announced the acceleration of Bacaba, the first project in our copper development pipeline, by six to nine months. I am pleased to now announce that our second project at Salobo has also been accelerated by one year. This clearly demonstrates the strength of our project portfolio and our ability to mitigate risk, optimise, and deliver projects with low capital requirements and high returns.”

The CPF project is an expansion of the existing Salobo operation, leveraging the high-quality ore body and existing infrastructure, thereby reducing execution risk. Salobo is the largest copper operation in Brazil and a key long-life asset for VBM. By adding a new flotation circuit that separates waste rock at an early stage of the processing flow, CPF will reduce grinding requirements at Salobo, address grinding capacity constraints, improve metallurgical recovery, and enable higher processing rates. With lower average energy and water use compared with other methods, the project is expected to reduce the environmental impact of the Salobo operation.

As part of the Salobo strategic plan, the total volume of material moved at the mine is expected to increase by approximately 7%, supported by a number of initiatives, including the deployment of new autonomous haulage equipment. VBM obtained the construction permit for the CPF project from IBAMA, Brazil’s environmental agency, ahead of schedule, allowing the project to begin earlier than planned.

Wheaton Precious Metals has agreed to provide $40 million in funding to VBM to finance part of the project’s capital expenditure. Payments will be made in two tranches of $20 million each, subject to the achievement of project milestones. VBM and Wheaton have agreed that these payments will replace future milestone-based payments under the existing Salobo streaming agreement. That agreement previously provided for Wheaton to potentially pay VBM up to $8 million per year for 10 years if a high-grade mining plan were implemented.

After reviewing the CPF project plan, VBM simplified the project scope, reducing the estimated capital expenditure to approximately $215 million, down from the initial estimate of $225-275 million. With the funding from Wheaton, VBM’s capital expenditure is expected to be approximately $175 million. The project has a low capital intensity of $5,000-$6,000 per tonne of copper equivalent, well below the industry average.

“Both parties will genuinely benefit, both Wheaton and VBM,” said Usmar. “The $40 million contribution further enhances the project’s economic attractiveness, while Wheaton will benefit from increased gold by-product production as a result of CPF. We appreciate Wheaton’s support, which reflects our strong long-term relationship and shared confidence in the value that the CPF project will generate at Salobo.”

“Salobo has been a core asset for Wheaton for many years, and we are pleased to support the development of the CPF project. This reflects our commitment to investing alongside high-quality partners in a range of opportunities that…”

More from 16 August 2026 →

Cite this article