The Jakarta Provincial Government (Pemprov DKI Jakarta) continues to strive towards building a more integrated flood control system, ranging from river normalisation and the construction of water control infrastructure to strengthening community preparedness for extreme weather.

Amidst the complexity of the challenges faced, the various steps undertaken by the Jakarta Provincial Government are part of a long-term effort to realise a more resilient, safe, and comfortable city for all its residents.

Strengthening Pumping Stations

The Jakarta Provincial Government is reinforcing flood control infrastructure through the deployment of water pumps, the strengthening of polder systems, and the maintenance of water bodies to ensure drainage systems function optimally during high rainfall. As of 13 March 2026, Jakarta possesses 668 stationary pump units distributed across 243 locations. Additionally, the Jakarta Water Resources Agency (SDA) has deployed 537 mobile pumps across five administrative regions. The presence of mobile pumps is vital for managing inundation in areas unreachable by stationary pumps.

Head of the Jakarta Water Resources Agency, Ika Agustin, stated that all flood control equipment is prepared to operate at maximum capacity, particularly when high-intensity rain hits Jakarta. “We are ensuring that all flood control devices can function optimally before, during, and after high-intensity rainfall. Flood mitigation is a collaborative effort that requires speed, precision, and infrastructural readiness,” said Ika, as quoted from the official Jakarta Provincial Government website.

The Jakarta Provincial Government is also implementing the JakTirta Project 2025-2027, which includes the construction of 20 pumping stations with a total of 61 new pump units at several strategic points. This project will increase flood control capacity by up to 148 cubic metres per second. One of the primary projects currently underway is the Ancol Pumping Station Water System in Pademangan, North Jakarta. This facility will increase pumping capacity by 25 cubic metres per second through five new pump units, raising the water flow capacity in the area from 15 to 40 cubic metres per second.

While inspecting the construction of the facility on Tuesday (7/4/2026), Jakarta Governor Pramono Anung emphasised that increasing pump capacity is a crucial step in strengthening the flood control system in Jakarta’s coastal areas. “This addition is vital to enhance the system’s ability to handle high water volumes,” he explained. According to Pramono, the Ancol Pumping Station is designed to accelerate water flow towards the sea while strengthening protection against tidal flood threats in the Ancol and Pademangan areas. The presence of this facility is expected to keep strategic areas safe and support the smooth activities of residents and businesses.

Dredging Rivers and Reservoirs

The Jakarta Provincial Government is also accelerating the dredging of rivers, canals, reservoirs, lakes, and retention basins to restore storage capacity and smooth water flow. As of 13 March 2026, the volume of dredging across Jakarta’s five administrative cities reached 123,393 cubic metres. This activity began on 2 January 2026 and will continue to expand to various other water bodies. Throughout 2025, the total dredging volume was recorded at 919,17um cubic metres. The Jakarta Water Resources Agency deployed 260 excavators and 465 dump trucks to support these activities.

One dredging location is the Kali Sepak Kembangan, or Kali Uwungan, in West Jakarta, which has a width of nine metres. Dredging is being conducted across a six-metre width with a safety distance of 1.5 metres from the bank edge to reduce landslide risks. Overall, the planned dredging volume for Kali Sepak is 7,458 cubic metres across a length of 1,243 metres, divided into three segments. “This dredging aims to maintain smooth water flow, considering Kali Sepak is an important estuary connected across regions, including the Cengkareng Drain,” said Pramono.

River Normalisation

In addition to pumps and dredging, the Jakarta Provincial Government is preparing medium-term measures through river normalisation. Three rivers are of particular focus: the Ciliwung River, the Krukut River, and the Cakung Lama Canal. River normalisation for the Ciliwung is being conducted alongside the central government. According to data from the Jakarta Water Resources Agency, the total planned construction of Ciliwung normalisation embankments reaches 33.69 kilometres. Of that amount, approximately 17.14 kilometres have been realised.

“Ciliwung River normalisation will soon commence alongside the central government through embankment construction. Normalisation of the Krukut River and Cakung Lama Canal are targeted to begin this year,” stated Pramono.

Meanwhile, the Coordinating Minister for Infrastructure and Regional Development, Agus Harimurti Yudhoyono (AHY), stated that Ciliwung normalisation is approximately 52 per cent complete. Out of the total 33 kilometres, 17 kilometres have been completed, with about 16 kilometres remaining to be finalised. “Currently, construction and revitalisation, including river normalisation of approximately 33 kilometres, are underway; 17 kilometres have been completed, leaving 16 kilometres remaining,” said AHY.

One of the challenges in completing normalisation is land acquisition. Therefore, collaboration between the central government and the Jakarta Provincial Government is essential. “The challenge is always land. The Deputy Minister of Public Works also mentioned that land acquisition is often hindered and not yet ‘clean and clear’. This is why collaboration between the central and Jakarta governments is so vital, and the community must also be involved in this massive effort,” he concluded.

More from 2 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/to-tackle-jakarta-flooding-provincial-government-relies-on-pumps-dredging-and-river-normalisation-1780867615)
Originally published by detikcom (https://news.detik.com/berita/d-8514970/atasi-banjir-dki-pemprov-andalkan-pompa-pengerukan-normalisasi-sungai), translated from Indonesian
Print