Tito Urges Local Governments to Resolve Land Issues for 7,952 Disaster-Recovery Homes in Sumatra

| Source: detikcom Translated from Indonesian | Infrastructure
Tito Urges Local Governments to Resolve Land Issues for 7,952 Disaster-Recovery Homes in Sumatra
Image: detikcom

Muhammad Tito Karnavian, head of the Task Force for the Acceleration of Rehabilitation and Reconstruction (Satgas PRR) following the Sumatra disasters, has urged local governments to speed up the resolution of land issues for the construction of 7,952 permanent homes in 2026. Certainty over locations and the legal status of land use are considered essential to prevent delays in building homes for affected residents.

Tito said local governments played an important role in providing land for residents who had lost their homes and land, lived in disaster-prone areas or needed to be relocated. Land that could be used included assets belonging to the central government, local governments, villages and state-owned enterprises (SOEs), as well as land with cultivation rights (HGU), in accordance with applicable regulations.

“What may need assistance is the land. Local governments are responsible for preparing it. The President’s instruction is that all state land—whether owned by the central government, local governments, villages or SOEs—as well as private land with HGU status, must be made available for the construction of homes for disaster victims,” Tito said in a written statement on Thursday (22 October 2026).

Tito made the remarks at a coordination meeting on accelerating Sumatra’s recovery at the Ministry of Home Affairs in Jakarta on Wednesday (21 October).

In 2026, the Ministry of Housing and Settlement Areas (PKP) allocated Rp2.21 trillion to build 7,952 landed houses, along with public infrastructure, facilities and utilities. The programme is divided into 54 work packages, including 29 construction packages.

However, construction remains at an early stage. As of 8am on 21 October 2026, physical progress stood at 3.48%, while budget realisation had reached 8.92%, or about Rp197 billion.

Tito said that although work had begun, around 250 units could not yet be built because their land was not ready. The issue had been identified in West Sumatra and in Bener Meriah, Gayo Lues and North Aceh regencies. He asked provincial governments to help provide land in Padang city and Agam Regency so construction could proceed.

In North Aceh, four sites still face land-related obstacles. An asset valuation by a public appraisal firm has not reached agreement with residents, requiring the valuation to be conducted again. Resolving the issue is urgent, as the regency has also proposed building more than 4,000 permanent homes in 2027.

Similar difficulties have affected the construction of community-built homes facilitated by the Ministry of Housing and Settlement Areas in partnership with corporate social responsibility programmes, SOEs and regionally owned enterprises. Of the 500 units allocated in North Aceh, 240 have been completed, while land for 162 units in two villages has yet to be acquired.

If sites are not made available soon, construction of those units could be moved to Aceh Tamiang, following new mapping and the preparation of a site plan.

In Aceh Tamiang, the proposed construction site is in an oil-palm plantation area. The government is processing the transfer of the land’s status to a local-government asset and changing its designated use from plantation to residential.

“We have coordinated with the Ministry of Agrarian Affairs and Spatial Planning/National Land Agency (ATR/BPN) and held several meetings to process the transfer of the land’s status to local-government ownership, as well as to revise the regional spatial plan (RTRW) so that the area’s designation changes from plantation to residential,” said Teddy Paul H. Siagian, acting director-general of rural housing at the Ministry of Housing and Settlement Areas.

Resolving land issues will also determine the progress of construction in 2027. The Ministry of Housing and Settlement Areas estimates a need for 17,654 permanent homes, with a budget of Rp5.19 trillion, including an additional 592 units for Pidie Jaya Regency.

The requirement has been submitted through an updated action plan to the Ministry of National Development Planning (PPN)/Bappenas and will be discussed with local governments and the Satgas PRR in November 2026.

More from 22 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/tito-urges-local-governments-to-resolve-land-issues-for-7-952-disaster-recovery-homes-in-sumatra-1792666367)
Originally published by detikcom (https://news.detik.com/berita/d-8719332/kejar-target-7-952-huntap-bencana-sumatera-tito-minta-pemda-bereskan-lahan), translated from Indonesian
Print