Jakarta - The Supreme Audit Agency (BPK) will conduct a special audit of the road maintenance project along Java’s North Coast (Pantura). BPK Member IV Ali Masykur Musa said the inspection was necessary because the size of the budget was suspicious. “The maintenance budget is very large and is prepared every year,” he told Tempo on Wednesday, 17 July 2013.

According to Ali, the audit of the project carried out by the Ministry of Public Works is targeted for completion in the coming months. The audit will also examine why the project is budgeted for every year. “We will see whether the work is being done properly or not,” he said.

Under the 2013 Revised State Budget, funds for road repairs along the Pantura totalled Rp 1.2 trillion. The funds are for a 1,300-kilometre stretch.

The national secretariat coordinator of the Indonesian Forum for Budget Transparency (Fitra), Uchok Sky Khadafi, said the road repairs had deliberately been turned into an eternal project. The proof, he said, was that over the past four years, of the total budget of Rp 1.2 trillion, Rp 256 billion had been used to repair the same route in the past three years. The route is in the area from Karawang to Losari, Cirebon.

In his view, the potential for irregularities could arise because oversight was lax. Moreover, every year the budget proposed by the Ministry of Public Works was always approved by the House of Representatives without an evaluation being carried out. “The House has not been critical. Yet it should evaluate budget realisation every year,” he said yesterday.

Public Works Minister Djoko Kirmanto argued that damage to roads along Java’s Pantura was caused by trucks carrying loads exceeding their capacity. Vehicles using the route should not weigh more than 10 tonnes. “In fact, many are over 10 tonnes, so it is understandable that the road gets damaged quickly,” he said yesterday.

He claimed there had been no budget irregularities in the road repairs. To prevent road repairs from being needed every year, he said, the Ministry of Public Works would replace the road with concrete construction that could last for up to 10 years. Djoko said the BPK was welcome to inspect the ministry he headed. “That is indeed the BPK’s job,” he said.

Deputy Chairman of House Commission V, which oversees public works, Muhidin Mohammad Said, said he would ask Minister Djoko Kirmanto for an explanation after the recess. “We will hold a meeting to conduct an evaluation,” he said yesterday.

Muhidin stressed that funding for maintenance of the Pantura route still had to be budgeted. “The Pantura route is a national road that must be maintained. There has to be a budget for it,” he said.

More from 18 July 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/the-suspiciously-eternal-pantura-road-project-1374080400)
Originally published by Tempo Interactive (http://www.tempo.co/read/news/2013/07/18/058497413/Proyek-Abadi-nan-Mencurigakan-Jalan-Pantura), translated from Indonesian
Print