The Full Story of the LRT City Problem and Danantara Summoning ADHI

| Source: CNBC Indonesia Translated from Indonesian | Property
The Full Story of the LRT City Problem and Danantara Summoning ADHI
Image: CNBC Indonesia

The problem of the LRT City project, which has not been handed over to consumers, continues to unfold. The issue has now garnered attention at the government level, after Minister of Housing and Residential Areas (PKP) Maruarar Sirait and Danantara Indonesia stepped in.

The problem began with complaints from consumers who purchased units in several LRT City projects. They claim they have not received the units they bought and are asking the government to assist with the full refund process.

During an audience with Maruarar, consumers from various LRT City projects voiced their grievances. A consumer from LRT City Tebet, Ajeng, said she stopped her payments because the project showed no progress. “Since it was never completed, I decided not to continue my payments. Because I saw that what was promised never showed any progress at all. Even when I visited the location, construction had completely stopped,” Ajeng said.

Her decision led to problems with the bank. She said debt collectors pursued her to her workplace. “I ended up being chased. I was chased all the way to my office. It was very embarrassing and now my OJK SLIK score is 5,” she said.

A similar issue was raised by a consumer of LRT City Ciracas. He said he signed the Sale and Purchase Agreement (PPJB) in 2019, but until 2026, the promised unit had not been received. “I signed the PPJB in 2019 and until 2026, about 7 years now, I have not received my right to my unit. So the definite step is we are asking for a full refund for all the costs we have incurred,” he said.

Meanwhile, LRT City Cibubur consumer Adityo complained about the difficulty of communicating with the developer, PT Adhi Commuter Properti Tbk (ADCP). He said consumers who visited the ADCP head office were only met by security guards. “We actually agreed to ask for a refund from ADCP. Our disappointment is, firstly, ADCP is very difficult to contact. Secondly, when our colleague went to the ADCP head office, it was empty and only met by a security guard,” Adityo said. He requested the Ministry of Housing’s assistance to facilitate the consumer refund process.

ADCP President Director Indra Syahruzza Nasution admitted the company’s financial condition is under pressure. He said he had only been studying the company’s condition for about two weeks. From a financial performance perspective, he said ADCP’s liquidity is severely depressed, making refunds difficult. When asked about the company’s cash flow, Indra answered that ADCP’s cash flow is negative. He mentioned that ADCP’s operational cash flow up to June 2026 was recorded at minus approximately Rp900 million.

Hearing this, Minister Maruarar Sirait stated he would propose that the Supreme Audit Agency (BPK) conduct an investigative audit of ADCP. He said he would meet with the BPK and propose an examination of the company to obtain clear data. “I think this is Adhi Karya. I happen to be meeting with the BPK tonight at 8 PM. I will ask, can we just audit them, perhaps an investigative audit. I will propose it, I think as a minister I can propose it. So we have a clear database, clear data,” Maruarar said.

He stressed that an investigative audit is needed so the government can get a complete picture of the company’s condition, including the reasons for its difficulty in processing refunds. Maruarar also emphasised that the government will map out all the problems faced by consumers, including the possibility of criminal elements. He instructed his staff to coordinate with the prosecutor’s office to examine potential legal violations. “If there is a legal element, those responsible must be held accountable. No compromise. I don’t want to play games with the people’s fate. If anyone tries to play games, we will enforce the law to the fullest extent,” Maruarar stressed.

The LRT City issue then escalated to Danantara. Head of the State-Owned Enterprises Supervisory Board and COO of Danantara, Dony Oskaria, summoned the management of PT Adhi Karya (Persero) Tbk (ADHI), the parent company of ADCP, to discuss the developments and various public complaints regarding LRT City. The meeting addressed the problems experienced by the public so that they receive attention and are immediately followed up. ADHI was also encouraged to strengthen communication with residents and relevant stakeholders. “All public complaints must be followed up immediately. Communication with residents also needs to be strengthened, so that existing problems can be resolved immediately,” Dony said. He stressed that problem resolution needs to be carried out quickly while building good communication with the residents. According to him, ADHI must ensure that area management is carried out responsibly. Development must not only be completed physically, but must also provide a sense of security, comfort, and certainty for the community. LRT City is part of an integrated residential area development connected to mass transportation infrastructure.

More from 13 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/the-full-story-of-the-lrt-city-problem-and-danantara-summoning-adhi-1786625541)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/market/20260813165804-17-759062/duduk-perkara-masalah-lrt-city-hingga-danantara-panggil-adhi), translated from Indonesian
Print