Tebing Tinggi Realises Regional Transfer Funds Through 170 Post-Disaster Recovery Packages
The Tebing Tinggi municipal government is targeting all 170 post-disaster recovery activity packages to be under contract by mid-September 2026. The procurement acceleration is intended to ensure the additional Regional Transfer Funds can be promptly used to address roads, rivers, and other infrastructure affected by the disaster.
Deputy Head of the National Command Post for the Sumatra Post-Disaster Rehabilitation and Reconstruction Task Force, Air Vice-Marshal Ridha Hermawan, said accelerating the procurement process is key to ensuring the budget quickly produces the work needed by the community.
“The utilisation of additional Regional Transfer Funds in Tebing Tinggi City needs to be accelerated. Accelerating the procurement process is a key factor in improving budget realisation,” Ridha said in a statement on Friday (28/8/2026).
Tebing Tinggi City has received additional Regional Transfer Funds amounting to Rp107.34 billion. As of 21 August 2026, Rp81.31 billion had been allocated for recovery activities, while realisation had only reached Rp800.08 million, or approximately 0.98 percent of the allocated budget.
The budget has been prepared through 170 activity packages using three procurement mechanisms. A total of 26 packages are being processed through tenders, 90 packages use direct procurement, and 54 packages are being handled through e-purchasing.
Infrastructure restoration received the largest allocation at Rp70.28 billion. The remaining budget has been allocated to the education sector at Rp3.74 billion, health at Rp3.09 billion, and agriculture at Rp727.74 million.
In the infrastructure sector, the work is focused on eight regional road sections that sustained moderate damage. The additional Regional Transfer Funds are also being used to address river siltation caused by sedimentation as well as damage to river protection structures at eight severely damaged locations and four moderately damaged locations.
To ensure the budget is used optimally, the Sumatra Post-Disaster Rehabilitation and Reconstruction Task Force team conducted special monitoring and evaluation in Tebing Tinggi City on Wednesday (26/8/2026). The team inspected affected roads, river normalisation sites, plans for retaining wall construction, and points where river flow has narrowed.
In addition to roads and rivers, the recovery also covers Gambir Market and Sakti Market. The damage status of both markets has been upgraded from light to moderate, and their handling has been accommodated in the Ministry of Trade’s action plan for the 2027 fiscal year.
Ridha emphasised that the Tebing Tinggi municipal government still has Rp26.02 billion in additional Regional Transfer Funds that have not yet been allocated. Based on coordination with the Directorate General of Regional Financial Development at the Ministry of Home Affairs, the budget will be included in the revised regional budget while remaining directed towards priority recovery needs.
“The success of Regional Transfer Fund utilisation is not only measured by budget absorption, but also by output achievements and its impact on restoring access, reducing disaster risk, and reviving community economic activity,” Ridha concluded.
Source: jawawa.id (https://jawawa.id/newsitem/tebing-tinggi-realises-regional-transfer-funds-through-170-post-disaster-recovery-packages-1787910791)
Originally published by detikcom (https://news.detik.com/berita/d-8638308/tebing-tinggi-realisasikan-dana-tkd-lewat-170-paket-pemulihan-pascabencana), translated from Indonesian