Tarutung-Sipirok Route Reopens as Permanent Repairs to Subsided Road Are Rushed

| Source: detikcom Translated from Indonesian | Infrastructure
Tarutung-Sipirok Route Reopens as Permanent Repairs to Subsided Road Are Rushed
Image: detikcom

Transport access along the Tarutung-Sipirok-Padangsidimpuan route at Antur Mangan, Sipirok district, South Tapanuli regency, North Sumatra, has reopened after being cut off by a road collapse. Emergency measures widened an alternative route to restore public mobility and vehicle traffic as quickly as possible.

The road at STA 14+150 subsided at around 6pm on Sunday (18 October) after heavy rain triggered a landslide. The incident cut off traffic and left a six-wheeled vehicle trapped in the collapsed section.

Access was restored by widening a diversion, filling and compacting material, and installing steel plates reinforced with aggregate. The measures have allowed both smaller and larger vehicles to use the route again.

“Emergency work has successfully reopened the road to both smaller and larger vehicles. Permanent repairs must now be expedited, alongside regular monitoring to prevent further landslides or road collapses,” Brigadier General Fadjar Tjahjono, head of the South Tapanuli Monitoring and Evaluation Team for the Post-Disaster Acceleration Task Force for Rehabilitation and Reconstruction in Sumatra (Satgas PRR), said in a written statement on Sunday (24 October 2026).

Field personnel, heavy-equipment operators, contractors and consultants supported the reopening. Three excavators, two vibro rollers, one motor grader and five dump trucks were deployed to speed up the work and keep the route usable.

Although traffic has resumed, safety measures on the temporary route need to be strengthened, particularly to reduce the risk of vehicles skidding. The Satgas PRR has proposed adding aggregate to the section laid with steel plates, as well as regularly checking the road surface and the load-bearing capacity of the diversion.

Further work will focus on building a retaining wall reinforced with bored piles to restore the road to its original alignment. The work must take account of slope stability, road strength, drainage and the risk of ground movement if heavy rain returns.

Before the road collapsed, work on the retaining wall was already under way, with bored piles installed and excavation carried out for the pile cap. Progress was temporarily hampered because an electricity pole stood in the path of the widened diversion. Once the issue was addressed, work to reopen access could continue.

The Satgas PRR has urged the PPK 2.2 project officer, contractors, supervisory consultants, local government and relevant agencies to strengthen coordination so that permanent repairs meet technical requirements. Supplies of Class A aggregate, selected fill and sheet piles must also be secured to prevent delays.

Accelerating permanent repairs and implementing technical risk-mitigation measures are essential to keeping the Tarutung-Sipirok-Padangsidimpuan route safe, protecting connectivity and sustaining local economic activity.

More from 25 October 2026 →

Cite this article