Targeted for July Operation, Minister Dody and Brantas Abipraya Accelerate Completion of Sekolah Rakyat in Bogor Regency

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
Targeted for July Operation, Minister Dody and Brantas Abipraya Accelerate Completion of Sekolah Rakyat in Bogor Regency
Image: VIVA.co.id

The Minister of Public Works (PU), Dody Hanggodo, through an assignment to PT Brantas Abyland (Persero), is continuously pushing for the accelerated construction of the People’s School in Sipak Village, Jasinga District, Bogor Regency, West Java.

Dody aims for the project to be ready for operation by July 2026, in preparation for the 2026/2027 academic year. He emphasised that the construction of this People’s School is a tangible form of the government’s commitment to developing superior human resources.

“The Ministry of Public Works wants to ensure that this educational facility is built quickly and with high quality, so that it can be immediately utilised by the community and support equitable access to education,” Dody stated in his briefing on Tuesday, 30 June 2026.

Built on 6.96 hectares of land with hilly contours at an altitude of approximately 161 metres above sea level, this integrated education area is designed to accommodate up to 1,080 students across primary, junior high, and senior high school levels. The surrounding mountain panorama provides a comfortable learning atmosphere while supporting a healthy and sustainable educational environment.

Brantas Abipraya’s Corporate Secretary, Dian Sovana, stated that the construction of the People’s School is a real form of the company’s contribution to providing high-quality educational infrastructure that directly impacts the community.

“Through the construction of the People’s School in Bogor Regency, we continue to provide high-quality, safe educational facilities, completed on time so they can be immediately utilised by the public,” said Dian.

He explained that the construction of the Bogor People’s School presents unique challenges, as the project site was previously a forested area with contoured land and quite extreme slope gradients. Before construction could begin, the project team had to undertake land maturation work using the cut-and-fill method for approximately two months.

Furthermore, high rainfall intensity and limited access to the location have also posed challenges in the mobilisation of materials and the execution of construction. Therefore, to ensure that work continues optimally, Brantas Abipraya is implementing mature construction planning, strengthened field coordination, and the consistent application of safety and quality standards.

“Currently, work is focused on the building finishing stage and the reinforcement of retaining walls to guarantee the safety of the area, which is situated in a hilly region,” he added.

Tags: bisnis

More from 30 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/targeted-for-july-operation-minister-dody-and-brantas-abipraya-accelerate-completion-of-sekolah-rakyat-in-1782823957)
Originally published by VIVA.co.id (https://www.viva.co.id/bisnis/1909967-ditargetkan-beroperasi-juli-menteri-dody-brantas-abipraya-kebut-penyelesaian-sekolah-rakyat-di-kabupaten-bogor), translated from Indonesian
Print