Tanah Datar Regent Shifts Additional TKD to Restore Irrigation for 68 Hectares of Rice Fields and Repair Two Bridges
Tanah Datar Regent Eka Putra, together with representatives of the Task Force for the Acceleration of Rehabilitation and Reconstruction (Satgas PRR) and the Ministry of Home Affairs, is seeking a solution so that Additional Special Allocation Funds (TKD Tambahan) can be allocated to strengthen the irrigation flow serving 68 hectares of rice fields as well as to address damaged bridges.
This emerged during a visit by Eka Putra, along with Fernando H. Siagian, Head of the Regional Budget Planning Sub-Directorate for Region I, and Kastorius Sinaga, Media Coordinator of the PRR Task Force for Sumatra, to the river channel in the Bukit Patah Gigi area, Nagari Padang Laweh Malalo, Batipuh Selatan District, Tanah Datar Regency, West Sumatra, on Wednesday, 22 July 2026.
Near the sabo dam on the river, BWS V Padang has laid pipes as a diversion channel carrying water to residents’ farmland. However, this emergency irrigation channel is still lined with blue tarpaulin as a temporary solution to keep water flowing to the farmland. “This irrigation channel is extremely important — 68 hectares of farmland depend on water from this flow,” said Eka Putra.
Local resident Mawardi urged that the emergency tarpaulin be replaced soon. “It will not last long. We ask for a budget from the government so that this irrigation channel becomes more permanent. All the farmers depend on this irrigation,” he told Tempo.
The proposal received a positive response from Eka Putra, who said he was ready to adjust the priorities for using the Additional TKD in line with the field mapping results so that a permanent irrigation network can be built promptly.
According to Eka Putra, the field inspection showed that the community’s needs have evolved compared with the initial budget planning stage. Therefore, some of the Additional TKD priorities need to be adjusted, particularly to build an irrigation network supporting the productivity of some 68 hectares of rice fields.
This statement was welcomed by the Ministry of Home Affairs representative Fernando, who affirmed that the budget reallocation is permissible as long as it refers to Circular of the Minister of Home Affairs Number 900.1.1/10059/SJ. The circular already regulates adjustments to budget usage under certain conditions, including addressing urgent post-disaster needs.
The budget shift, Fernando continued, can subsequently be formalised through an amendment to the regent’s regulation, although conditions in the field allow for adjustments. “As long as it remains in accordance with prevailing regulations,” said Fernando. “Regional governments are given room to allocate the Additional TKD as long as the aim is post-disaster rehabilitation and reconstruction.”
A reallocation is also possible for two bridges damaged by the follow-on floods in May 2026. The first is the Tanjung Enau Bridge in Nagari Taluak, Lintau Buo District. The severing of that connecting access had left 81 families facing isolation, as the main route to their settlement could not be traversed by four-wheeled vehicles.
While the permanent bridge cannot yet be used, residents built a simple bridge themselves from coconut tree trunks. The regency government then coordinated with the Indonesian Army to build a Bailey bridge as a temporary route so that residents’ activities, including school needs and logistics distribution, could continue.
The second location, the Pulau Bridge in Nagari Lubuk Jantan, Lintau Buo Utara District, was also severely damaged, forcing farmers to take much longer alternative routes to bring in their harvest from the rice fields.
Seeing these conditions, the Regent of Tanah Datar adjusted the allocation of the Additional TKD so that construction of both bridges can proceed promptly. Each bridge has been allocated a budget of Rp 4 billion through the budget reallocation mechanism.
The Detailed Engineering Design (DED) documents for both bridges have been prepared. The Tanah Datar Regency Government is next preparing the construction process in accordance with prevailing regulations so that the works can be carried out promptly while upholding the principle of accountability.
“The use of the Additional TKD for the two bridges is also being monitored by the Tanah Datar District Prosecutor’s Office. The supervision is being carried out to ensure that the budget adjustment process through to the implementation of the works complies with the rules,” said Eka Putra.
The normalisation of the Bukit Patah Gigi river itself remains part of the central government’s handling through the Balai Wilayah Sungai (BWS) V Padang. Therefore, the results of the field inspection will also serve as material for coordination so that central and regional efforts proceed in tandem.
Minister of Home Affairs Tito Karnavian, who also heads the PRR Task Force, stated that the acceleration of rehabilitation and reconstruction has been set out in the Master Plan (Renduk), with a budget of Rp 100.1 trillion prepared and a target of completion by 2028. The budget is earmarked for 32 ministries and agencies tasked with handling post-disaster rehabilitation and reconstruction in Sumatra.
Tito asked the ministries to move quickly to accelerate rehabilitation and reconstruction. He also ensured that the PRR Task Force will continue to check the progress of the master plan programme every week. “This step is important to ensure the programme runs according to plan, including resolving the problems being faced,” said Tito.