Sumatra Electricity Critical, 510 MW Batang Toru Hydroelectric Plant Operations Accelerated
The Ministry of Energy and Mineral Resources (ESDM) is accelerating the operation of the Batang Toru Hydroelectric Power Plant (PLTA) with a capacity of 510 Megawatts (MW) to strengthen the Sumatra electricity system. This move follows disruptions at the plant caused by flooding in November 2025.
Deputy Minister of Energy and Mineral Resources, Yuliot, personally inspected the progress of this national strategic project in South Tapanuli Regency, North Sumatra. He confirmed that technical testing of the plant is currently being conducted in parallel with the resolution of remaining administrative issues to ensure the plant can be connected to the national grid as soon as possible.
“This is our acceleration effort for the provision and reliability of energy nationally. Specifically, the energy condition in the Sumatra region is quite critical, so we require anticipatory measures. Given the limited availability of other primary energy sources, we have the Batang Toru Hydroelectric Plant which can go on-grid,” Yuliot stated in an official release on Friday (31/7/2026).
As a result of the disaster that occurred late last year, five transmission towers collapsed, damaging the reliability of the regional power supply. The Ministry is overseeing the accelerated reconstruction of the transmission lines to ensure that power from the Batang Toru plant can be absorbed optimally.
“The reconstruction of these transmission lines is being accelerated so that electrical energy from the Batang Toru plant can be distributed optimally into the Sumatra transmission network,” he added.
The project, valued at IDR 21.6 trillion and managed by PT North Sumatera Hydro Energy (NSHE), was also previously hindered by administrative sanctions; however, the company has now received the green light to continue construction. Currently, field teams are focusing on technical testing, which requires water impoundment as a prerequisite for turbine operation.
“The testing being conducted requires water impoundment, as is necessary for a hydroelectric plant. Without impoundment, testing cannot be performed. Therefore, we are conducting the resolution of administrative matters and the execution of testing in parallel,” he further explained.
In addition to ensuring reliability in the Sumatra region, the operation of this plant is key for the government in pursuing its New and Renewable Energy (EBT) mix targets. Currently, the national clean energy mix stands at 16-17%, while the target for the end of 2026 is set at 21%.
“If we do not implement these accelerations, the 21% energy mix target will not be achieved by the end of the year,” he concluded.