Sumatra Disaster Recovery Accelerated, Rp21.42 Trillion Allocated for Roads and Bridges

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
Sumatra Disaster Recovery Accelerated, Rp21.42 Trillion Allocated for Roads and Bridges
Image: VIVA.co.id

The government is accelerating post-disaster rehabilitation and reconstruction in Aceh, North Sumatra and West Sumatra, allocating Rp21.42 trillion through the Ministry of Public Works for the 2026 fiscal year. The funds will be used to repair damaged infrastructure, including roads, bridges and rivers, as well as clean-water facilities and temporary housing for affected residents.

Progress on the disaster response was discussed at a coordination meeting of the Task Force for Accelerating Post-Disaster Rehabilitation and Reconstruction, chaired by Home Affairs Minister Tito Karnavian. The meeting also covered economic recovery for local communities through support for micro, small and medium-sized enterprises (MSMEs).

Tito said that, of the 33 ministries and agencies involved in the post-disaster response, 29 had received budget allocations for 2026 totalling around Rp30 trillion. The other four ministries and agencies had not requested funding.

In addition to central government funding, the three affected provinces have received unexpected expenditure funds (BTT) and additional regional transfers (TKD) in two rounds, on the President’s instructions.

Rp21.42 Trillion for Infrastructure Recovery

Ministry of Public Works Secretary-General Apri Artoto reported that the effective budget ceiling for disaster response in Sumatra in 2026 stood at Rp21.42 trillion. It is divided among four main sectors: water resources, Rp7.85 trillion; roads, Rp6.64 trillion; human settlements, Rp4.05 trillion; and strategic infrastructure, Rp2.89 trillion.

As of 25 October 2026, work had been completed on two of the 33 national road sections being handled. Work on the remaining sections was continuing, with average progress of 59.04 per cent.

Of the 20 bridges being repaired, five had been completed: three in Aceh and two in West Sumatra. Work on the remaining 15 bridges was continuing, with average progress of 63.29 per cent.

Apri stressed the importance of ensuring that reconstruction proceeds effectively.

“All of this progress reflects the state’s tangible presence. Our challenge is to complete all the work on time, with construction that is more resilient and sustainable,” Apri said.

Tags: berita

More from 28 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/sumatra-disaster-recovery-accelerated-rp21-42-trillion-allocated-for-roads-and-bridges-1793184749)
Originally published by VIVA.co.id (https://www.viva.co.id/berita/nasional/1939249-pemulihan-bencana-sumatera-dikebut-rp2142-triliun-digelontorkan-untuk-jalan-hingga-jembatan), translated from Indonesian
Print