South Jakarta City Hall Office Without AC for Nearly 4 Months, Awaiting Repair Budget
JAKARTA — The South Jakarta City Government office, specifically Block A, has been unable to use room cooling (AC) optimally for nearly four months after the genset transformer caught fire at the end of 2025.
South Jakarta Mayor M. Anwar said that the repair plan is being discussed with Commission A of the DKI Jakarta DPRD, so they cannot yet proceed with direct procurement.
To date, the repairs are still awaiting budgeting.
He explained that the repair process cannot be carried out like ordinary procurement because the damage occurred due to an unforeseen event or force majeure.
“Because this is force majeure, a disaster. Yes, the substation next door exploded,” Anwar said.
As a result of the damage, the electricity supply for the room cooling system has not fully recovered.
Civil servants (ASN) in the South Jakarta City Government environment are still working without adequate AC support.
Head of the General and Protocol Section of the South Jakarta Administrative City, Poulinawati, said that they have been using a mobile transformer from PLN as a temporary solution.
“Since the incident, a mobile transformer from PLN was immediately brought in. But its capacity is 1,000 kVA. After we checked, that capacity seems insufficient to back up the entire office operations,” Poulinawati said.
Although the conditions are not ideal, she assured that services to the public continue to run.
It is known that the fire occurred in the genset transformer room of the South Jakarta City Hall building on Jalan Prapanca Raya, Petogogan, Kebayoran Baru, on Sunday (28/12/2025) around 06:24 WIB.
Head of the South Jakarta Fire and Rescue Agency (Gulkarmat), Asril Rizal, said the incident began with an explosion sound heard at the location.
Seven fire trucks with 28 personnel were deployed to extinguish the fire, which was brought under control around 06:50 WIB.
As a result of the fire, the main electrical facilities for room cooling were damaged and have not fully recovered to this day.
Source: jawawa.id (https://jawawa.id/newsitem/south-jakarta-city-hall-office-without-ac-for-nearly-4-months-awaiting-repair-budget-1776909163)
Originally published by Kompas (https://megapolitan.kompas.com/read/2026/04/23/08023651/kantor-pemkot-jaksel-hampir-4-bulan-tanpa-ac-tunggu-anggaran-perbaikan?utm_source=ABC&utm_medium=rss), translated from Indonesian