Singapore to Build Five Power Plants Worth Rp75 Trillion as It Braces for Energy Crisis
Singapore plans to build five new natural-gas power plants by 2031 to prepare for a surge in electricity demand and strengthen energy security. The move is a strategic response to the risk of regional energy supply disruptions that could threaten the reliability of the country’s electricity supply.
According to Channel News Asia on Monday (26 October 2026), the five plants are scheduled to begin operating in stages between 2026 and 2031. The additional facilities are expected to increase Singapore’s electricity generation capacity by about 26% from its current level of around 12 gigawatts (GW).
The new plants are needed as electricity demand rises. Singapore’s Energy Market Authority (EMA) said peak demand reached 8.6 GW by August 2026. It is projected to rise to between 9.9 GW and 13 GW by 2031.
The increase is driven mainly by energy-intensive sectors, including semiconductor manufacturing and data centres, as well as the growing use of electric vehicles.
The EMA said: “This increase is primarily driven by new demand from energy-intensive sectors, such as semiconductor manufacturing and data centres, as well as the wider adoption of electric transport.”
Alongside the five plants, the Singapore Government is reviewing a proposal for an additional gas-fired power plant, targeted to begin operating in 2032. The move is intended to ensure that electricity supply capacity can keep pace with long-term energy demand.
The generation expansion is being accompanied by substantial investment in the electricity grid. Singapore has allocated S$5.3 billion, or around Rp75.18 trillion, to expand the grid between 2025 and 2029. This is about 11 times the allocation for the previous five-year period.
The investment includes plans to build seven new transmission substations by 2031. The transmission cable network will also be expanded from about 7,700 kilometres to 9,100 kilometres by 2030 to improve the reliability of electricity distribution.
Beyond gas-fired generation, Singapore is developing solar energy and energy storage. Solar capacity currently stands at 2.3 gigawatt-peak (GWp), with a target of 3 GWp by 2030 and 4 GWp by 2035. Energy storage capacity is targeted to increase from 350 megawatt-hours (MWh) to more than 1 gigawatt-hour (GWh) by 2030.
Singapore is also seeking to diversify supply through low-carbon electricity imports. Sembcorp Utilities has received conditional approval to import 1.3 GW of electricity, potentially sourced from offshore wind farms in Vietnam and solar power in Malaysia.
To strengthen gas supplies, Singapore plans to increase its liquefied natural gas (LNG) regasification capacity from 10 million tonnes to 15 million tonnes a year. A second LNG terminal at Jurong Port is expected to begin operating in 2030.
Tan See Leng, Singapore’s Minister for Trade and Industry responsible for Energy and Industry, said the Government had prepared various measures to address the risk of supply disruptions.
“So, for Singapore… we can remain calm and keep moving forward,” he said, emphasising that energy security is a national priority.
Supply disruption risks are a concern because Singapore still relies on natural gas for about 95% of its electricity needs. Indonesia has reportedly begun reducing gas supplies to Singapore, although the amount is less than 2% of the city-state’s daily gas requirements.
Source: jawawa.id (https://jawawa.id/newsitem/singapore-to-build-five-power-plants-worth-rp75-trillion-as-it-braces-for-energy-crisis-1793065837)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20261026172537-4-779589/siaga-krisis-energi-singapura-bangun-5-pembangkit-listrik-rp75-t), translated from Indonesian