Singapore Deal Dropped as Natuna’s Mako Gas Project Is Fast-Tracked and Pipeline Production Begins
Jakarta, CNBC Indonesia — The Mako Gas Field development project in the Duyung Working Area, offshore Natuna, has entered the domestic production phase for its pipeline. Production of 80 kilometres of pipe to support the project, whose output will be supplied to the domestic market, has begun in Batam.
The pipes are being produced by the WNEL production-sharing contract (PSC) consortium, comprising West Natuna Exploration Ltd, which holds a 25 per cent stake, and PT Nation Natuna Barat, which holds 75 per cent.
According to a statement from SKK Migas Head Djoko Siswanto on Sunday (1 November 2026), the project includes the construction of production facilities at two locations: PT PAL Indonesia’s yard in Surabaya and a facility in Batam. The project’s groundbreaking is scheduled for next month and is expected to be led by Energy and Mineral Resources Minister Bahlil Lahadalia.
Over the next two years, the project is expected to complete several stages of work, from offshore drilling in Natuna and construction of production facilities to the installation of 80 kilometres of subsea pipeline. Once completed, the Mako field is expected to produce 111 million standard cubic feet of gas per day (MMscfd).
Initially, gas from the Mako field was planned to be sent to Singapore, as at the time there was only one pipeline route connecting Natuna with the neighbouring country.
The supply plan changed after construction of the West Natuna Transmission System (WNTS) pipeline, linking Pemping Island with Batam, was completed. With the approval of the Energy and Mineral Resources Minister, all gas produced at Mako will now be supplied to meet domestic demand, particularly in the electricity sector in Batam and surrounding areas.
The decision was made despite reports that gas prices in Singapore are higher than those in the domestic market. Prioritising domestic supply is said to be consistent with national interests and the mandate of Article 33 of the 1945 Constitution.
Source: jawawa.id (https://jawawa.id/newsitem/singapore-deal-dropped-as-natunas-mako-gas-project-is-fast-tracked-and-pipeline-production-begins-1793501421)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20261101081709-4-781222/batal-ke-singapura-proyek-gas-mako-natuna-dikebut-pipa-mulai-produksi), translated from Indonesian