Rp3.5 Trillion AI Data Centre Project in Jatiluhur Halted, Purwakarta Regent: Sort Out the EIA First!
The construction project for an artificial intelligence (AI) based data centre owned by BDx Data Centres in the Jatiluhur area, Purwakarta, West Java, cannot proceed until all government-mandated requirements are met.
Purwakarta Regent Saepul Bahri Binzein emphasised that the developer must first complete the Environmental Impact Assessment (Amdal) documents and Building Approval (PBG). “Sort out the EIA first. Once the EIA is handled, then handle the PBG,” he stated, as reported on Saturday (3/10/26).
According to Saepul, the EIA is necessary to ensure that both the construction and the operation of the data centre do not cause environmental impacts that violate regulations. Currently, the Purwakarta Regency Government is waiting for the EIA consultants from BDx to conduct the document discussions.
In addition to the EIA, the developer is also required to secure the PBG before construction can continue. Consequently, as long as these two requirements remain unfulfilled, the work on the BDx AI data centre project in the Jatiluhur area cannot proceed and must remain temporarily halted.
The Purwakarta Regent’s statement follows the previous groundbreaking ceremony for BDx Data Centres’ AI Campus 2 (CGK4) project. The ceremony for the project, valued at Rp3.5 trillion, took place in Jatiluhur, Purwakarta, on Tuesday (22/9/26).
The event was attended by the Governor of West Java, Dedi Mulyadi, and the Regent of Purwakarta, Saepul Bahri Binzein. However, the groundbreaking ceremony did not automatically permit construction to proceed; the local government maintains that the developer must fulfil environmental and building requirements before the project continues.
Previously, the Governor of West Java, Dedi Mulyability, spoke out regarding the temporary halt of the Rp3.5 trillion AI-based data centre construction in Jatiluhur, Purwakarta. Dedi emphasised that the suspension of the BDx Data Centres project was not caused by bureaucratic hurdles from the Purwakarta Regency Government or the West Java Provincial Government. According to him, the project was paused because the consultants had not yet completed the licensing data.
Dedi Mulyadi made this statement to clarify the controversy surrounding the halt of the data centre construction. “When I asked yesterday, the Building Permit (IMB) had not been issued. Has the EIA been issued? Not yet. So I said, do not proceed with construction yet. Because the permit hasn’t been issued. Where is the fault? With the Purwakarta Local Government? No. The fault lies with the consultants, as even when I arrived, they had not submitted the data,” said Dedi Mulyadi, as quoted on Saturday (3/10/26).
Source: jawawa.id (https://jawawa.id/newsitem/rp3-5-trillion-ai-data-centre-project-in-jatiluhur-halted-purwakarta-regent-sort-out-the-eia-first-1791013910)