Road in Pulogadung Subsides for Five Months, Residents Fear Worsening Damage
The concrete on Jalan Cinta, Pulogadung, East Jakarta, has split apart due to land subsidence. Residents report that the road has been damaged for months.
“Initially, the subsidence was minimal, but it continues to shift and widen every day. This road has been damaged for five months, yet there has been no handling,” said the Head of RT 11 RW 03 Pulo Gadung, Warjono, as reported by Antara on Tuesday (7/7/2026).
Residents are concerned that the worsening damage could lead to traffic accidents and even fatalities if not addressed immediately. Warjono noted that the subsidence, which initially occurred at only a few points, has now expanded to cover almost 100 metres.
To avoid the risk of accidents, residents and local officials have closed the road to four-wheeled vehicles. Currently, only motorcycles are permitted to pass through using a alternating system, as the remaining road width is only about 1 metre.
“This impacts the local environment and residents, affecting both four-wheeled and two-wheeled vehicles, as well as MSME traders, as they can no longer pass through here and must take detours. This is a main road that is usually used every day. Therefore, all road users typically pass through here,” he explained.
Furthermore, this collapsed road serves as one of the alternative routes used daily by the community as a primary access point to residential areas and various economic activities.
Warjoking suspects the road damage was triggered by the dredging of the Pulogadung River, which was performed too deeply. As a result, the soil structure on the riverbank became unstable and experienced gradual landslides that dragged the road surface with it.
“At first, it was just a small amount, but it has shifted and grown like this,” said Warjono.
Although no residential houses have experienced structural shifts so far, several local facilities have begun to be affected. Some drainage channels have cracked, the road surface continues to subside, and waste collection points have also sustained damage.
According to him, there have been no casualties from the road condition so far. However, residents are increasingly worried because the passable part of the road is becoming narrower, while the area is a densely populated neighbourhood used daily by vehicles and children.
“We fear that at any time, motorcyclists or children might fall towards the river if the road shifts further,” said Warjono.
Warjono hopes that the government, through the relevant agencies, will immediately carry out permanent repairs to Jalan Cinta before the situation worsens.
Temporary Measures
The Mayor of East Jakarta, Munjirin, stated that he has coordinated with the Water Resources Agency (SDA) to handle the land subsidence at the edge of the water flow. Officials from the Water Resources Agency have already begun temporary measures at the site.
“I have coordinated with the Water Resources Agency, directly with the Head of the Agency. It will be followed up by the Water Resources Agency,” said Munjirin on Monday (6/7).
He stated that temporary handling is currently underway. The exact cause of the subsidence—whether due to soil movement or erosion caused by the river flow—is not yet known.
“For the time being, the situation is being handled by the East Jakarta Water Resources Sub-department using wooden piles (dolken),” he added.
Source: jawawa.id (https://jawawa.id/newsitem/road-in-pulogadung-subsides-for-five-months-residents-fear-worsening-damage-1783418121)
Originally published by detikcom (https://news.detik.com/berita/d-8563776/jalan-di-pulogadung-amblas-5-bulan-warga-waswas-kerusakan-makin-parah), translated from Indonesian