RI Expenditure to Rise Despite Uncertainty

| Source: The Jakarta Post

The Jakarta Post

Raras Cahyafitri, Jakarta

More money will pour into the oil and gas sector next year to boost production, while concerns such as contract uncertainty will intensify.

Oil and gas contractors in the country have proposed US$25.6 billion in total investment for next year, 32 percent higher than the $19.3 billion spent this year, according to the acting chief of the Upstream Oil and Gas Regulatory Special Task Force (SKKMigas), Johannes Widjonarko.

Disbursement is a challenge as the business is known for its high risks. SKKMigas data showed the $19.3 billion spent this year was lower than the budgeted $23 billion.

“Various matters caused the lower realization, including unfruitful tenders, land availability and operational factors. We’re carrying out revamping work so they can work faster,” Johannes said.

Indonesia has been trying to boost oil output to meet growing demand, which has forced the country to import the commodity and has seen its trade balance tainted partly due to the purchases.

Oil production reached 826,000 barrels per day (bpd) this year, lower than the targeted 840,000 bpd. Delayed on-stream schedules, a declining rate of production in aging fields, unplanned shutdowns and shipping problems have contributed to the failure to meet the output target, according to Johannes.

In the early 2000s, Indonesia produced 1.3 million bpd of oil. The decline in production is mainly due to aging wells and difficult areas in deep waters in the east of the country.

Uncertainty over contract expiry is another factor overshadowing the sector in Indonesia. Global energy think-tank Wood Mackenzie pointed out in a recent report that up to 20 oil and gas production sharing contracts (PSCs) are scheduled to expire in the next five years. The PSCs accounted for 635,000 barrels of oil equivalent per day (boepd) in 2013, equal to 30 percent of the country’s current production.

The report said the government’s decision over the contract of Offshore Mahakam’s PSC held by Total E&P Indonesie, which will expire in 2017, would be a critical precedent for future PSC extensions.

State-owned oil firm Pertamina has said it is ready if the government asks to run the block after its contract expiry. Pertamina was appointed to run the Siak Block, the contract of which was held by PT Chevron Pacific Indonesia and expired in late November. The government made a decision to terminate the contract on the date of expiry.

Lukman Mahfoedz, the Indonesia Petroleum Association (IPA) chairman, said the government needed to give a clear timeline of when it would announce extensions or terminations.

More from 30 December 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ri-expenditure-to-rise-despite-uncertainty-1388336400)
Originally published by The Jakarta Post (http://www.thejakartapost.com/news/2013/12/30/expenditure-rises-despite-uncertainty.html)