Revitalisation of Denpasar Customary Village Cemetery Wall Nearly Complete

| Source: detikBali Translated from Indonesian | Infrastructure
Revitalisation of Denpasar Customary Village Cemetery Wall Nearly Complete
Image: detikBali

The revitalisation of the wall at Setra Agung Badung cemetery in Denpasar Customary Village is nearly complete. The project, undertaken by CV Mitra Teknik Utama under a contract worth around Rp12.96 billion, is targeted for completion on 7 December 2026.

Denpasar’s Head of Housing, Settlement Areas and Land Affairs (Perkim), Putu Tony Marthana Wijaya, said progress in the 25th week, covering 27 October to 2 November 2026, had reached 94.501%.

“The plan was 94.426%; actual progress has now reached 94.501%,” Tony said when contacted by detikBali on Tuesday (10 November 2026).

This means the revitalisation work is slightly ahead of schedule. Recorded progress was 0.075 percentage points higher than the target for the same period.

The project is scheduled to run for 210 calendar days. Work began on 12 May 2026 and is due to be completed on 7 December 2026, according to the notice to proceed (SPMK).

A detikBali visit to the site found that the cemetery wall’s revitalisation was looking orderly. The footpath, lined with ornamental plants along the cemetery grounds, had also been arranged.

However, several statues remained wrapped and had not yet been uncovered. Electrical cables around the site also still appeared disorderly. Some hung down low, potentially obstructing pedestrians.

More from 10 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/revitalisation-of-denpasar-customary-village-cemetery-wall-nearly-complete-1794318613)
Originally published by detikBali (https://www.detik.com/bali/berita/d-8747240/revitalisasi-tembok-kuburan-desa-adat-denpasar-hampir-rampung), translated from Indonesian
Print