Residents Visit PLN Tanjungpinang Office at Midnight to Protest Power Cuts
Dozens of residents went to the customer service implementation unit (UP3) office of state-owned electricity company PT PLN on Jalan Bakar Batu in Tanjungpinang, Riau Islands, in the early hours of Wednesday (14 October), prompted by continuing power cuts.
The residents, most of them young people, gathered at the Tanjungpinang UP3 office because outages were still affecting the city, known as Kota Gurindam. Electricity was cut from 2.15pm on Tuesday (13 October) and was not restored until about 3.35am on Wednesday (14 October).
“We’ve had enough. If rolling blackouts lasted only a short time, that would be one thing, but this has gone too far and the power has been off for a long time,” Ardi shouted outside the Tanjungpinang UP3 office in the early hours of Wednesday.
Ardi and several friends demanded an explanation from the Tanjungpinang UP3 about the continuing power cuts on Bintan Island, which includes Tanjungpinang and Bintan Regency.
He said sudden outages, without notice and affecting areas unevenly, had damaged household electrical appliances.
“We can see that the outages in Tanjungpinang are uneven. Some places get power back quickly, while others remain without it for a long time. Appliances at home have been damaged by the power going on and off,” he said.
In an explanation to residents, Heru Eka Saputra, PLN Tanjungpinang UP3’s team leader for occupational health and safety and security, said Batam and Tanjungpinang had separate electricity systems.
He said Bintan Island and Tanjungpinang received electricity through an interconnected transmission and distribution network linking the power supply between Batam and Bintan. The network runs through an undersea 150-kilovolt cable more than 17.9 kilometres long, carrying electricity from Batam power plants such as the Tanjung Kasam coal-fired power plant, via Ngenang Island, Tanjung Sauh, Tanjung Tal and Tanjung Uban on Bintan.
“Electricity supply has not yet been fully delivered to Bintan Island. For now, the island’s power is being supplied by the diesel power plants there,” he said.
Electricity demand on Bintan, including in Tanjungpinang, is estimated at around 90–100 megawatts, while the Tanjungpinang UP3’s reserve capacity is only about 30–34 MW. The resulting shortfall has necessitated rolling power cuts.
The residents eventually dispersed from the Tanjungpinang UP3 office under the supervision of Tanjungpinang Police officers.
However, they said they would return to the office on Wednesday afternoon (14 October) for a larger demonstration, demanding clarity over the continuing power cuts.
Source: jawawa.id (https://jawawa.id/newsitem/residents-visit-pln-tanjungpinang-office-at-midnight-to-protest-power-cuts-1791942661)
Originally published by CNN Indonesia (https://www.cnnindonesia.com/nasional/20261014073354-20-1415049/warga-datangi-kantor-pln-tanjungpinang-tengah-malam-protes-pemadaman), translated from Indonesian