Relocation of Residents Affected by Blora’s Karangnongko Dam Project Held Up by Forestry Ministry Permit; MP Vows to Pursue Issue at National Level

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
Relocation of Residents Affected by Blora’s Karangnongko Dam Project Held Up by Forestry Ministry Permit; MP Vows to Pursue Issue at National Level
Image: VIVA.co.id

Jakarta – House of Representatives Commission V member Danang Wicaksana Sulistya has pledged to oversee the relocation of residents affected by construction of the Karangnongko Dam in Blora, Central Java.

Danang will take the residents’ concerns to the national level through working meetings and hearings with ministries partnered with Commission V.

He made the statement after conducting a recess visit in Blora, one of the constituencies he represents. He said recess visits give MPs an opportunity to hear public concerns and move parliamentary meetings from the House complex in Senayan to their constituencies.

Accordingly, issues gathered during the recess will be pursued through official forums with the relevant ministries and institutions.

“I will present these concerns at working meetings and hearings with our partners in Commission V,” Danang said, as quoted on Saturday (31 October 2026).

Commission V works with several ministries and institutions: the Ministry of Public Works; the Ministry of Housing and Settlements; the Ministry of Transmigration; the Ministry of Villages and Development of Disadvantaged Regions; the Ministry of Transportation; the Meteorology, Climatology and Geophysics Agency (BMKG); and the National Search and Rescue Agency (Basarnas).

On the relocation of residents affected by the Karangnongko Dam, Danang said a replacement site had already been identified. The land is in a Special Purpose Forest Area (KHDTK) currently managed by Gadjah Mada University (UGM).

The Gerindra Party’s Yogyakarta regional chair said the land had received permission to be used as a relocation area for 535 households. However, its use still requires approval from the Ministry of Forestry to change the land’s designated function.

Construction of the Karangnongko Dam affects 1,037 land plots across five villages: 17 plots in Mendenrejo, 328 in Ngrawoh, 177 in Nginggil, 372 in Nglebak and 143 in Megeri.

A total of 535 households in the affected area have been identified as needing assistance, including certainty over their relocation site.

In addition to pursuing the relocation issue, Danang is also urging faster infrastructure development through the Regional Socio-Economic Infrastructure Development (PISEW) programme.

He made the call while inaugurating a PISEW project on the road linking Sunggun Hamlet and Parengan Hamlet with Mendenrejo Village in Kradenan district, Blora.

Tags: berita

More from 31 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/relocation-of-residents-affected-by-bloras-karangnongko-dam-project-held-up-by-forestry-ministry-permit-mp-1793440278)
Originally published by VIVA.co.id (https://www.viva.co.id/berita/nasional/1940041-relokasi-warga-terdampak-proyek-bendungan-karangnongko-blora-terkendala-izin-kemenhut-dpr-janji-kawal-sampai-pusat), translated from Indonesian
Print