Red Tape Bogs Down Gas Projects
The Jakarta Globe by Tito Summa Siahaan
Indonesian Petroleum Association chairman Lukman Mahfoedz recalled that back in the 1970s, the construction of the Badak Liquefied Natural Gas plant in East Kalimantan took about three years between the project commencement and the first shipment of product to a Japanese buyer.
Today, project completion in the oil and gas industry can take much longer.
Lukman noted that now, the period between discovery of initial reserves and project completion could take several years or even decades.
The period for the Tangguh LNG project in West Papua was 16 years, while huge natural gas reserves found in the Masela block off Maluku in 2000 are not slated to come on line until 2018.
“The story of Badak LNG to show we are not without success stories but they are becoming increasingly rarer,” Lukman said. Still, he acknowledged the different situation the industry faces today and says making comparisons was not be helpful.
“To label the industry as moving backward would be too harsh. The situation is different, it is more complex,” he added.
Yanto Sianipar, senior vice president at Chevron Pacific Indonesia, supported Lukman’s remarks, saying the implementation regional autonomy and a sweeping reform after the 1998 movement had a game-changing impact for the industry. “Now, the industry must engage with multiple stakeholders,” he added.
The government has acknowledged the situation and is looking to remedy it.
Agung Wicaksono, a special assistant in the President’s Delivery Unit for Development Monitoring and Oversight (UKP4), said an oil and gas project needs 64 permits from 17 different government institutions and it involves 600,000 pages of documents.
Agung said the problem lies in the rigid hierarchical relations between different ministries.
“There will be little issue if a project is being handled by the same ministry or two ministries under the same coordinating minister, but when it goes through different coordinating ministers or even involves the regional governments, then things get more complicated,” Agung added.
Work is underway to simplify permit issuance in the industry, Agung said, adding that the government will cut the number of permits required for using land in protected forests, waste disposal, and the use of foreign vessels for offshore activities, among others.
Johanes Widjonarko, the interim head of upstream oil and gas regulator SKKMigas, said the government must also consider removing property tax for exploration activities. He added that there were several cases where the property taxes paid were higher than the actual investment being made for exploration.
Property tax burdens investment for exploration activities, as the phase generates no revenue, Johannes said.
Lukman of the Indonesian Petroleum Association said Indonesia is also being left behind in the use of modern technology. “In terms of technology advancement, we are 15 to 20 years behind,” Lukman said who is also the president director of Medco Energy.
Outdated equipment and resources means Indonesia lacks the capability to exploit and extract hydrocarbon reserves in more technically challenging locations.
Edi Hermantoro, the director general for oil and gas at the Energy and Mineral Resources Ministry, said challenges in the industry are common.
“Investors always talk about the difficulties of expanding in Papua, but actually the situation is not that much different than in the 1960s when they first ventured in remote areas of Sumatra and Kalimantan.”
Edi said improving the synergy between institutions is a job for the government.
CPI’s Yanto agreed, saying, “the challenges are well-identified and the priorities are clear, the issue here is communication and it needs improving.”