Reconstruction of flood-damaged Islamic boarding school in West Aceh to be completed by October
Meulaboh (ANTARA) - The West Aceh Regency Government targets the completion of the Babul Jannah Thalibul Ilmi Islamic boarding school, which was impacted by flash floods in Keutambang Village, Pante Ceureumen District, by the end of this coming October.
“As of early October, the progress of physical financing through regional transfer funds (TKD) has reached the stage of a 49 per cent down payment disbursement,” said the Acting Head of the West Aceh Regency Education and Dayah Office, Hendra Saputra, to journalists on Thursday.
The facilities and budget for the construction include two study halls with a budget of Rp672 million, and the construction of two male and female dormitories, each budgeted at Rp180 million. Additionally, the construction of two male and female sanitation facilities (MCK) is budgeted at Rp144 million each.
He stated that the local government is currently striving to accelerate the reconstruction progress of the Islamic boarding school (Dayah) infrastructure, which was previously destroyed by flash floods towards the end of 2025.
Hendra Saputra explained that the ongoing physical construction is focused on permanent concrete-based facilities to replace the old buildings that were swept away by floodwaters. “These buildings were previously totally destroyed and carried away by the flood currents, leaving only flat ground. Therefore, we are rebuilding them permanently with concrete structures so they can be fully and perfectly utilised by the students,” said Hendra.
He noted that all physical specifications have passed the survey and thorough planning stages by the consultant team. His office is optimistic that the project work can be completed ahead of the contract schedule.
“In accordance with the target and planning, we are endeavouring to complete this construction early; God willing, the 100 per cent target can be achieved by the end of October,” he concluded.
Source: jawawa.id (https://jawawa.id/newsitem/reconstruction-of-flood-damaged-islamic-boarding-school-in-west-aceh-to-be-completed-by-october-1790877326)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5767631/pembangunan-pesantren-terdampak-banjir-di-aceh-barat-tuntas-di-oktober), translated from Indonesian