Rajawali’s Long-Delayed Railway to Be Built in 2015

| Source: The Jakarta Globe

The Jakarta Globe By Muhammad Al Azhari

Construction of a $2 billion railway track in Sumatra is expected to start in 2015, according to a top company official, in a move that should help ease the transportation of coal.

The track will be built by a joint venture between Rajawali Corporation and state coal miner Bukit Asam, Rajawali’s managing director Darjoto Setyawan said on Thursday.

“We have cleared up all the licensing with Kereta Api Indonesia, but the project is still awaiting the valuation of a coal mine,” said Darjoto on the sidelines of an infrastructure forum in Jakarta.

Rajawali, which is owned by businessman Peter Sondakh, and state coal miner Bukit Asam will join hands to build two projects in Sumatra.

One project aims to develop a mine in Bangko Tengah, South Sumatra, which has an estimated 400 million tons of coal reserves. The project is being handled by Bukit Asam Banko, a joint venture between Bukit Asam, which holds a 65 percent interest, the local government, which controls 10 percent of the project, and Rajawali with a 25 percent stake.

The other project is a 307-kilometer railway track from Tanjung Enim, South Sumatra, to Bandar Lampung.

The track construction is being carried out by Bukit Asam Transpacific Railways. Bukit Asam controls 10 percent of the BATR railway venture, while Rajawali controls the remaining 90 percent through its subsidiary Rajawali Asia Resources.

However, the railway project cannot be commenced until an assessment is completed to determine the value of the coal mine. Darjoto said Deloitte has been appointed to assess the value of the mine.

In 2008, the mine was valued to be worth $1.21 per ton. However, as the price of coal has since changed, investors at Bukit Asam Banko requested a revaluation.

“We hope to settle this valuation matter by the end of the year,” Darjoto said.

Once the valuation is settled, BATR will still need to acquire land for the project, which is expected to take around one and a half years. Darjoto said he estimates groundbreaking will take place in 2015.

The railway project has secured financing from Chinese lenders. China Railway Group will control 10 percent of RAR, the Rajawali subsidiary, after the firm receives $1.3 billion in financing from a consortium of Chinese lenders consisting of the China Development Bank, the Export-Import Bank of China and the Industrial and Commercial Bank of China. The investment, which covers the total cost to build the train network including the price of wagons, rail lines, stations and equipment, stood at around $2 billion, Darjoto said.

Bukit Asam on Wednesday reported that its nine-month profit dropped as falling prices led to lower sales.

More from 1 November 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/rajawalis-long-delayed-railway-to-be-built-in-2015-1383238800)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/rajawalis-long-delayed-railway-to-be-built-in-2015/)
Print