The Ministry of Public Works (PU), through the North Sumatra National Road Implementation Agency (BBPJN), carried out emergency repairs after a road collapsed and was cut off at kilometre 29+900 on Section 1 of the North Tapanuli–Central Tapanuli regency boundary route, in Sibalanga village, North Tapanuli, North Sumatra.

The incident occurred at about 12.15pm local time on Friday, 23 October 2026, after heavy rain persisted for an extended period. The situation was compounded by increased traffic on the Tarutung–Sibolga route after damage and a collapse on the Tarutung–Sipirok road led to traffic being diverted onto a detour.

Public Works Minister Dody Hanggodo said maintaining connectivity was the government’s main priority during disaster emergencies, given the strategic role of roads and bridges in supporting public activity and logistics distribution.

“Connectivity is the lifeblood of the community. In a disaster, the most important thing is to keep access open so that residents can travel, humanitarian aid can reach them and logistics distribution is not interrupted,” Dody said in a statement on Thursday, 29 October 2026.

The landslide occurred beside a construction site for a retaining wall, which is being built on bored-pile foundations. Heavy rainfall from the afternoon until midnight caused the detour road to subside and collapse, temporarily making the main Tarutung–Sibolga route impassable.

No vehicles were directly hit by the landslide and no deaths were reported. However, the road closure disrupted access for residents travelling from the Tarutung area towards Simpang Rampah.

As an emergency measure, the North Sumatra BBPJN, contractor PT Hutama Karya and the North Tapanuli Police Traffic Unit repaired the road to restore public transport access.

The work included filling and compacting the road surface and installing six steel plates measuring 2 by 1 metres. The team deployed three excavators, one vibrating roller and five dump trucks. Materials used included Class A aggregate, selected fill, steel plates, 100 wooden piles and 100 geobags.

According to a progress report dated 27 October 2026 at noon, all emergency repairs to the 25-metre section had been completed, reaching 100 per cent of the planned work.

After the emergency work, access gradually recovered. Small four-wheeled vehicles were reported to be able to pass that evening, followed by larger vehicles at 11.30pm.

The field team faced several challenges, including limited space to widen the detour because of a resident’s boundary wall, as well as traffic congestion around the site, which hampered the movement of trucks carrying materials.

The Ministry of Public Works, through the North Sumatra BBPJN, continues to coordinate with relevant parties on road conditions to support public mobility and goods distribution and maintain connectivity along the Tarutung–Sibolga route.

The ministry advised road users to take care when passing the repair site, follow instructions from on-site officers, and take account of weather conditions and travel safety.

More from 29 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/public-works-ministry-completes-repairs-to-collapsed-road-on-tarutung-sibolga-route-1793245962)
Originally published by detikcom (https://news.detik.com/berita/d-8728950/kementerian-pu-rampungkan-perbaikan-jalan-amblas-di-tarutung-sibolga), translated from Indonesian
Print