Public Works Ministry Completes Reconstruction of Roads and Bridge in South-east Aceh

| Source: CNN Indonesia Translated from Indonesian | Infrastructure
Public Works Ministry Completes Reconstruction of Roads and Bridge in South-east Aceh
Image: CNN Indonesia

The Ministry of Public Works (PU) has completed three post-disaster connectivity infrastructure projects in South-east Aceh Regency, Aceh Province, with physical progress reaching 100 per cent.

The work covered the reconstruction of two road sections and the replacement of Lawe Mengkudu I Bridge in Ketambe District, to support the restoration of transport access and community activity.

Public Works Minister Dody Hanggodo said restoring connectivity was a top priority for the ministry in its post-disaster infrastructure response.

Roads and bridges play an important role in linking residential areas, facilitating residents’ mobility, and supporting the distribution of goods and services.

“Road connectivity is a top priority in post-disaster recovery. Restored infrastructure will help people carry out their daily activities, improve access to economic centres and public services, and support the recovery of the regional economy,” Dody said.

The road reconstruction covered two connected sections in Gampong Lawe Mengkudu, Ketambe District, South-east Aceh Regency: Lawe Ger Ger Road and Bener Berpapah Road. Together, they form a 1.075-kilometre project, from STA 18+325 to STA 19+400.

Lawe Ger Ger Road was reconstructed over 575 metres at a cost of Rp57.79 billion. Work then continued on 500 metres of Bener Berpapah Road, costing Rp17.26 billion. Both projects began in November 2025 and were fully completed in October 2026.

The connection between the two road sections is expected to improve transport access in the area. The roads are used to support residents’ mobility, transport agricultural produce, and reach economic centres and public services.

Connectivity was also restored through the replacement of Lawe Mengkudu I Bridge in Gampong Lawe Mengkudu, Ketambe District. The six-metre bridge was fully completed in October 2026, at a cost of Rp35.23 billion from the state budget.

The Ministry of Public Works said it would continue the phased response and restoration of infrastructure affected by the Sumatra disasters to ensure that inter-regional connectivity is restored.

More from 10 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/public-works-ministry-completes-reconstruction-of-roads-and-bridge-in-south-east-aceh-1794300657)
Originally published by CNN Indonesia (https://www.cnnindonesia.com/nasional/20261110143813-25-1425432/kemenpu-tuntaskan-rekonstruksi-jalan-dan-jembatan-di-aceh-tenggara), translated from Indonesian
Print