Public Works Minister Teams with Danantara to Rescue People's School Project Amid Contractor Cash Flow Issues
JAKARTA, KOMPAS.com — Minister of Public Works Dody Hanggodo has requested support from Danantara and Himbara banks to assist contractors facing cash flow difficulties in building People’s Schools (SR). This measure aims to ensure the completion of 93 SR Phase II sites by June 2026.
Dody made the statement after attending a coordination meeting on People’s Schools with Social Affairs Minister Saifullah Yusuf in Jakarta on Tuesday, 26 May 2026. The meeting was also attended by representatives from the Presidential Staff Office (KSP) and the Ministry of Communications and Digital (Komdigi).
According to Dody, financial support is needed to ensure construction work proceeds optimally amid cash flow constraints faced by some contractors. “For service providers experiencing cash flow issues, we have coordinated with Danantara to receive assistance from Himbara banks. Regarding labour, we will involve TNI Zeni support, as previously done in North Lombok SR sites, for locations with delayed progress to meet the completion targets,” Dody said.
As of 25 May 2026, the average physical progress of People’s School construction reached 62.63 per cent, with financial progress at 41.76 per cent. “After checking overall land readiness and other factors, Insha’Allah we aim to complete by June 2026. We will continue to push for all 93 sites to be fully operational to support the new school year in July 2026,” Dody added.
To accelerate construction, the Ministry of Public Works has formed a People’s School Construction Acceleration Task Force, increased workforce, and implemented a three-shift work system. Additionally, construction method innovations and cross-sector coordination have been strengthened.
As of 25 May 2026, the People’s School project has employed 71,579 workers.
The meeting also discussed strengthening digital learning infrastructure through collaboration between the Ministry of Public Works, Ministry of Social Affairs (Kemensos), and Ministry of Communications and Digital (Komdigi). Support includes providing internet networks and telecommunications infrastructure, including plans to install fibre optic networks at Phase II People’s School locations.