Public Works Minister Targets Trans-Sumatra Toll Road to Reach Aceh by 2028

| Source: CNBC Indonesia Translated from Indonesian | Infrastructure
Public Works Minister Targets Trans-Sumatra Toll Road to Reach Aceh by 2028
Image: CNBC Indonesia

The Ministry of Public Works (PU) is committed to connecting the Trans-Sumatra Toll Road from Lampung to Aceh. Currently, several sections of the Trans-Sumatra Toll Road remain unconnected.

Following a working meeting with Commission V of the House of Representatives (DPR), Minister of Public Works Dody Hanggodo stated that the government’s primary focus is to complete the Betung-Tempino-Jambi toll road, which connects South Sumatra and Jambi.

“That is what will be continued,” said Dody on Wednesday (2/9/2026).

Once completed, the government will proceed with the construction designs to connect other provinces along the main corridor through to Aceh.

“The final design is being finalised this year. So, the intention is that by next year, physical construction can hopefully begin, with the target spanning from Aceh to Lampung,” he asserted.

He also targeted the Trans-Sumatra Toll Road to be fully connected from Lampung to Aceh by 2028. However, several factors are being considered by the government, such as toll traffic.

“The target, as far as I know, is at the latest 2028. However, it depends on many things, including traffic and various other factors. As many ports are being developed, it might even be faster,” he added.

Remaining sections of the Trans-Sumatra Toll Road include:

  • Medan - Binjai section (North Sumatra)

  • Pekanbaru - Kandis - Dumai section (Riau)

  • Kisaran - Tebing Tinggi section (North Sumatra)

  • Sigli - Banda Aceh section (Aceh)

  • Binjai - Langsa section (Aceh and North Sumatra)

  • Bukittinggi - Padang Panjang - Lubuk Alung - Padang section (West Sumatra)

  • Pekanbaru - Bangkinang - Payakumbuh - Bukittinggi section (West Sumatra and Riau)

  • Tebing Tinggi - Pematang Siantar - Prapat - Tarutung - Sibolga section (North Sumatra)

  • Betung (Sp. Sekayu) - Tempino - Jambi section (Jambi and South Sumatra)

  • Jambi - Rengat section (Jambi and Riau)

  • Rengat - Pekanbaru section (Riau)

  • Simpang Indralaya - Muara Enim section (South Sumatra)

  • Lubuk Linggau - Curup - Bengkulu section (South Sumatra and Bengkulu)

  • Kayu Agung - Palembang - Betung section (South Sumatra)

Currently operational sections of the Trans-Sumatra Toll Road include:

  • Bakauheni - Terbanggi Besar (140 km)

  • Terbanggi Besar - Pematang Panggang - Kayu Agung (189 km)

  • Palembang - Indralaya (22 km)

  • Indralaya - Prabumulih (64 km)

  • Betung - Jambi Section 3 (Bayung Lencir - Tempino) (52.1 km)

  • Bengkulu - Taba Penanjung (16.7 km)

  • Pekanbaru - Dumai (132 km)

  • Medan - Binjai (17 km)

  • Binjai - Pangkalan Brandan (58 km)

  • Pekanbaru - XIII Koto Kampar (55.4 km)

  • Padang - Sicincin (35.4 km)

  • Indrapura - Kisaran (48 km)

  • Kuala Tanjung - Tebing Tinggi - Sinaksak (91 km)

  • Sigli - Banda Aceh Section 2-6 (49 km)

More from 2 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/public-works-minister-targets-trans-sumatra-toll-road-to-reach-aceh-by-2028-1788350228)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260902174355-4-764446/menteri-pu-punya-target-tol-trans-sumatra-lampung-tembus-aceh-di-2028), translated from Indonesian
Print