Public Works Minister Ensures Accelerated Infrastructure Recovery in Disaster-Hit NTT and Sumatra
Public Works Minister Dody Hanggodo is accelerating the handling of infrastructure affected by natural disasters in East Nusa Tenggara (NTT) and Sumatra. The Ministry of Public Works is applying a rapid response pattern from the earliest phase, namely opening road connectivity, restoring clean water supply, and ensuring public facilities return to function in parallel.
In handling the M 7.7 earthquake that struck Flores, NTT, in mid-August 2026, Dody went directly to Nagekeo Regency. He asked the regional government to immediately submit initial damage data maps without waiting for the entire data collection process to be completed.
“We are present at every disaster, because the President’s directive is clear that we must not grieve for too long, we must rise as quickly as possible. So I ask for complete data, the points. So that we can deploy teams immediately, can coordinate with heads of agencies, can directly check one by one and immediately work,” said Dody in a statement received on Saturday (22/8).
As of 16 August, nine national road sections affected by the earthquake had returned to functionality. Eight sections are on the Trans Flores route from Labuan Bajo to Ende and Maumere, while the other is the Ruteng-Reo-Kedindi section.
A total of 40 landslide points and four road body fracture points were handled. The NTT National Road Implementation Agency deployed seven excavators and four loaders to various affected locations.
Although main access could be opened, Dody still faced work at a number of points. One of them is the 4.1-kilometre Krica-Lidi section in Pulue Village which has at least 10 landslide points.
Two excavators and one pickup vehicle were deployed. As of 19 August, the joint team managed to break through one of the landslide points and clearing is still ongoing.
Handling does not stop at road connectivity. Restoration of basic services, especially clean water, is also a priority.
In Ende Regency, the piping network of the 2024 Presidential Instruction SPAM IKK Nangaba was damaged by the earthquake. Repairs began on 16 August and were completed the following night. Water then flowed again to household connections.
On Palue Island, Sikka Regency, around 7,000 residents in eight villages need clean water support. Four tanks with a capacity of 1,200 litres each were sent to the location.
Handling is not only carried out for emergency needs. The government is also preparing geoelectric surveys to find new groundwater sources so that water supply can be strengthened in the longer term.
Dody also encouraged inspection of public facilities. Personnel deployed to inspect affected buildings were increased from three to 14 people. Komodo Hospital, government offices, places of worship, and public facilities are among the buildings inspected.
Damage to irrigation networks is also a concern. In the Mbay Kiri Lanjutan Irrigation Area, tertiary channels were damaged along 250 metres and fractured at three points. Around 175 hectares of land were affected.
The series of handling shows the pattern promoted by Dody: access is opened first so that mobility resumes, while restoration of water, public facilities, and supporting infrastructure is carried out in parallel.
A similar handling pattern was previously implemented when disasters struck Aceh, North Sumatra, and West Sumatra at the end of 2025.
Based on Ministry of Public Works data as of 20 August 2026, all 107 affected national road sections in the three provinces have returned to functionality. All 43 affected national bridges have also returned to function.
For regional roads, 2,291 of 2,421 affected sections have returned to functionality, or 94.63 percent. Of the 1,184 affected regional bridges, the Ministry of Public Works detailed table records 827 have returned to function.
Restoration of clean water services also shows significant progress. A total of 178 SPAM included in the handling data have all been recorded as functional again, consisting of 71 SPAM in Aceh, 45 in North Sumatra, and 62 in West Sumatra.
Meanwhile for housing, 1,794 of 1,914 units in 18 locations have been completed. A further 120 units are still being handled in North Sumatra. Handling of 702 public facilities has also been recorded as complete.
These achievements are part of the work of the Ministry of Public Works under Dody which not only focuses on reopening access, but also restoring basic community services after disasters.
However, the work is not entirely complete. Of the 31 central government irrigation areas affected, 13 have been completed. For regional government irrigation areas, two of 65 locations are recorded as complete.
For national weirs, four of 14 affected locations have been completed. Meanwhile, three of 52 regional weirs have been completed.
This condition means Dody’s work continues after the emergency response phase ends. If in the first days the focus was opening roads and restoring basic services, the next stage is ensuring infrastructure rehabilitation continues.
The direction of handling is beginning to move towards mitigation to reduce the risk of damage when disasters occur again.
In the Mount Marapi area, West Sumatra, construction of eight first-phase sabo dams began in March 2026. Five are in Tanah Datar Regency and three others in Agam Regency.
The eight sabo dams are designed to have a sediment holding capacity of around 440,000 cubic metres.
The government plans to build 56 sabo dams in stages on 24 rivers throughout 2026-2029. The infrastructure is prepared to hold material and reduce impacts if Mount Marapi activity again triggers material flows to areas below it.
For Dody, speed in the first days is important because severed access also hampers distribution of aid and services to the community.
Source: jawawa.id (https://jawawa.id/newsitem/public-works-minister-ensures-accelerated-infrastructure-recovery-in-disaster-hit-ntt-and-sumatra-1787403056)