Public Works Minister Accelerates Recovery at Eight Landslide Sites on Tapan–Jambi Route

| Source: detikcom Translated from Indonesian | Infrastructure
Public Works Minister Accelerates Recovery at Eight Landslide Sites on Tapan–Jambi Route
Image: detikcom

The Ministry of Public Works is accelerating efforts to deal with landslides and road subsidence along the national road between Tapan and the Jambi border, in Nagari Jangki Ayam, Ranah Ampek Hulu district, Pesisir Selatan regency, West Sumatra. Of the eight sites affected by heavy rain on 9–10 October 2026, four have been cleared, while work is continuing at the other four.

Public Works Minister Dody Hanggodo said the work was being carried out through the West Sumatra National Road Implementation Agency (BPJN) to restore road connectivity disrupted by the overflowing Tapan River and landslides at several locations. He said restoring access to roads and bridges was a priority in the emergency response, to support local people’s activities and the distribution of logistics.

“We are working without pause to ensure that the isolation of the area can be addressed as quickly as possible. The safety of the public and the smooth movement of people are our priorities,” Dody said in a statement on Monday (12 October 2026).

To speed up the response, the West Sumatra BPJN deployed two excavators and two wheel loaders to clear landslide debris blocking the road and address the affected sites. Officials have also installed warning signs and police lines to protect road users.

On Monday (12 October), the West Sumatra BPJN task force and relevant parties continued clearing landslide debris and repairing sections of sunken road. Work is being carried out in stages, taking account of terrain, rainfall, slope stability and the safety of personnel.

Dody said heavy rainfall in the area was complicating the emergency response. It increased the risk of further ground movement, requiring each stage of the work to be undertaken carefully to protect personnel and ensure the response is effective.

The national road between Tapan and the Jambi border remains impassable while clearance and repairs at several sites are unfinished. Road users have been advised to postpone journeys along the route until access is declared safe and reopened.

The Ministry of Public Works, through the West Sumatra BPJN, is continuing to expedite the emergency response so that the national road can be restored as soon as possible. The effort forms part of the government’s commitment to maintaining connectivity between regions, supporting public activities and ensuring roads are safe and functional again after disasters.

More from 12 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/public-works-minister-accelerates-recovery-at-eight-landslide-sites-on-tapan-jambi-route-1791820329)
Originally published by detikcom (https://news.detik.com/berita/d-8704096/menteri-pu-percepat-pemulihan-8-titik-longsor-di-ruas-tapan-jambi), translated from Indonesian
Print