Indonesian Political, Business & Finance News

Public Outcry Over Tahura Djuanda Toilet Project, with Physical Works Deemed Inadequate for Rp118.5 Million Budget

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
Public Outcry Over Tahura Djuanda Toilet Project, with Physical Works Deemed Inadequate for Rp118.5 Million Budget
Image: VIVA.co.id

Bandung — The management of the Ir H Djuanda Grand Forest Park (Tahura Djuanda) in Bandung has confirmed that the contractor has not yet been paid for a project to build two public toilets, which went viral on social media and has a contract value of Rp118.5 million. The work will be audited by the Inspectorate once it is complete.

Tahura Djuanda Technical Implementation Unit (UPTD) head Lutfi Erizka said the sanitation facilities at Cadas Bugis and Curug Ciomas were still being built in accordance with the contract, running from 12 November to 11 December 2026.

Lutfi said his office had coordinated with the Inspectorate to provide oversight and check that the quality and quantity of the completed work meet requirements before any funds are disbursed.

“After handover, the Inspectorate will provide oversight and inspect the work, then audit it to determine whether the full amount should be paid or whether payment should be adjusted based on its assessment,” he said.

He also clarified the project’s value, which is funded through the Tahura Djuanda UPTD Regional Public Service Agency (BLUD) budget. The initial figure of Rp120 million was reduced to Rp118.5 million following negotiations.

“The Rp120 million figure was not final. After negotiations, the value was approximately Rp118.5 million,” Lutfi said.

The dispute over the two public toilets in the conservation area first emerged on social media, where users questioned whether the buildings’ appearance was commensurate with a budget of Rp120 million.

The public scrutiny drew the attention of West Java Governor Dedi Mulyadi on Tuesday (24 November 2026). He called for a thorough inspection and said payment must not be made if the quality of the work does not match its cost.

“We’ll check it. It certainly hasn’t been paid yet. If the project is poor and does not match the amount of money spent, we won’t pay,” Dedi said.

Dedi also instructed the Tahura Djuanda UPTD finance team to ensure that the project funds remain on hold until the audit is complete.

“Check directly with the finance department at Tahura to see whether this project has been paid for. If it hasn’t, don’t pay it yet; first audit the value of the work,” he said.

The work at each site is being carried out by CV Formosa Il Armeta, with around five workers at each location. The Inspectorate’s review is expected to determine whether all the work meets the contract specifications.

Tags: berita

More from 27 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/public-outcry-over-tahura-djuanda-toilet-project-with-physical-works-deemed-inadequate-for-rp118-5-million-1795719020)
Originally published by VIVA.co.id (https://www.viva.co.id/berita/nasional/1946693-heboh-bangunan-fisik-proyek-toilet-tahura-djuanda-dinilai-tak-sebanding-dengan-anggaran-rp-1185-juta), translated from Indonesian
Print