PT PII Guarantees Annual Payments of Rp339.9bn for Major Project
Bekasi, CNBC Indonesia — PT Penjaminan Infrastruktur Indonesia (Persero), or PT PII, is guaranteeing availability payments (AP) of up to Rp339.9 billion a year for 15 years for a vehicle-testing facility, or Proving Ground, project in Bekasi, West Java.
The guarantee is intended to ensure that the government’s payment obligations to the project company, PT Indonesia International Automotive Proving Ground (IAPG), are met in accordance with the terms of the public-private partnership (PPP) agreement.
PT PII acting president director Donny said the government guarantee covers the certainty of AP payments to the company, provided the facility meets the required service-level agreement (SLA) standards.
If payments are delayed or the government fails to meet its obligations, PT PII’s guarantee mechanism will settle the government’s financial obligations in accordance with the agreement.
“What is guaranteed is precisely the certainty of the government’s AP, or availability payment, to the business entity, provided it has met the expected SLA or service standards,” Donny said.
According to Donny, certainty of payment is an important factor in enabling companies to obtain financing from financial institutions. For the Bekasi Proving Ground project, PT IAPG secured overseas funding, including from the Japan Bank for International Cooperation (JBIC) and MUFG.
The guarantee gives investors and lenders confidence that a protection mechanism is in place for the government’s payment obligations throughout the contract period.
Heri Setiawan, director of government support and infrastructure financing management at the Finance Ministry’s Directorate General of Financing and Risk Management (DJPPR), said the Bekasi Proving Ground project has capital expenditure (capex) of nearly Rp2 trillion. Operational and maintenance expenditure (opex) is estimated at around Rp1 trillion over 15 years.
Project calculations put the government’s AP obligation at Rp339.93 billion a year for 15 years. The payments form part of the mechanism for the project company to recoup its investment.
Heri said the PPP scheme allows a company to build a project and secure financing independently. However, the government remains obliged to make payments under the contract if the company delivers services that meet the requirements.
For the Proving Ground project, the AP payments have been budgeted annually and are guaranteed by PT PII.
This means a PPP scheme does not make a project entirely free of fiscal consequences. The government does not need to provide all the investment funding upfront, but it remains committed to long-term payments through the state budget (APBN).
Heri said the government guarantee also aims to improve a project’s bankability. This is important because PPP projects generally have long tenors, while lenders need certainty about the government’s ability to meet its contractual obligations.
Alongside providing the guarantee, PT PII monitors the obligations of both the government and the project company, covering operational and financial matters.
Donny said not all project risks are borne by the government. Financing risks and the company’s ability to build the facility remain its responsibility, while the AP payment obligation is a government risk.
The division of risks is set out in the PPP agreement to ensure that each risk is borne by the party best placed to manage it.
Before the project began, PT PII was also tasked with helping prepare it through its Project Development Facility (PDF). This included preparing the business case, technical studies, selecting testing standards, financial modelling and transaction assistance.
Preparation of the Bekasi Proving Ground project through the PDF began on 18 April 2019, with transaction assistance continuing until financial close on 31 March 2023.
Donny said that in its 16 years of operation, PT PII had guaranteed 61 infrastructure projects, mobilising more than Rp572 trillion in investment.
The guarantees cover a range of sectors, including telecommunications, electricity, roads and waste management.