PT Inco expects to meet '07 production target

By Meghann McDonell

PT International Nickel Indonesia Tbk (PT Inco) expects to hit its full-year production target of 165 million pounds of nickel in matte despite an 11-day strike by union workers seeking higher compensation.

Workers returned to their posts at the company's Sorowako Mine on Sulawesi Island earlier this week and operations have returned to normal, the company said.

The company lost about 5 million pounds of nickel in matte production. Losses were minimized as mining and processing activities continued throughout the labor dispute.

About 500 members of FSP-KEP UK PT Inco initiated the job action Nov. 15, but five days later just 200 remained on strike, the company said.

In a presentation to shareholders Monday, the company said that it is still in the process of reviewing the cost of bringing its third hydroelectric facility, the Karebbe Dam project, online.

The project's start-up costs will now exceed the $275 million to $280 million initially expected, the company said.

PT Inco said in October the Karebbe project, which will help increase metal production by 25 to 35 percent, will be delayed to the first half of 2011 from its initial start-up date of March 2010.

Construction of the dam was halted in January 2006 pending the receipt of a forestry permit that was granted in September this year.