Progress of Jakarta LRT Phase 1B Velodrome–Manggarai reaches 92.76 percent

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Progress of Jakarta LRT Phase 1B Velodrome–Manggarai reaches 92.76 percent
Image: Antara (Indonesian)

Jakarta (ANTARA) – PT Waskita Karya (Persero) Tbk reported that progress on the Jakarta LRT Phase 1B Velodrome–Manggarai project has reached 92.76 percent. Paulus Budi Kartiko, Director of Operations II of Waskita Karya, said that as the contractor responsible for civil integration, track, systems, and operations, the company reaffirms its commitment to accelerate the project while prioritising safety and security. ‘Construction safety, both in securing balance cantilever construction and for road users, must be prioritised,’ he said in a statement in Jakarta on Wednesday.

Paulus said that the company, together with PT Jakarta Propertindo (Persero) (Jakpro), has begun a series of Testing and Commissioning (T&C) of the LRT Jakarta Phase 1B Velodrome–Manggarai system some time ago. One of them was conducting a track test along a 3.6 km route connecting Velodrome Station with Pramuka Station.

‘In the course of the work, the main challenge (urban constraint) we face as a contractor includes Jakarta’s dense traffic and limited work space. Therefore, our solution is to optimise night-time working hours, which demand focus and innovation in safety systems and work systems; we see this as a constraint to be managed, not avoided,’ he said.

During the track testing, one area traversed was an overpass above the Wiyoto-Wiyono Toll Road at kilometre 1+700 to 2+100. To protect traffic conditions on the toll road during construction, the company innovated by using a balance cantilever method with spans of 120 metres. Similarly, monitoring surveys and chambers were carried out daily.

‘The Wiyoto-Wiyono crossing has become one of the most important icons in the track tests recently. The success signals progress for Indonesia’s construction sector to weave public transport with the existing active line amid Jakarta’s busy activity,’ he said.

Paulus said coordination with Jakpro, as project owner, continues to be strengthened so that the T&C sequence can run smoothly. This phase is important because its aim is to ensure how ready the LRT Jakarta system is to carry tens of thousands of passengers daily.

He disclosed that the track tests showed the trains could run smoothly from Velodrome to Pasar Pramuka, powered entirely by electricity.

‘The good cooperation with Jakpro as owner ensures the track tests – which have already been conducted twice – proceed without hindrance. Like Jakpro’s principle of always prioritising sustainability in its projects, these train runs will also serve as an internal evaluation to prepare for the next testing steps,’ he said.

Meanwhile, Jakpro’s Chief Executive Iwan Takwin said the company has carried out a series of T&C that cover systematic and structured testing of all components and subsystems before commercial operation commences, from the track, signaling, electrical, communications, to operational integration.

‘Every metre on the elevated LRT Jakarta Phase 1B track is our responsibility to the people of DKI Jakarta, who will rely on LRT daily. Therefore, the T&C phase must be prepared very thoroughly,’ said Iwan.

Construction of the Jakarta LRT Phase 1B with the Velodrome–Manggarai route began in October 2023 with a total investment of Rp4.1 trillion. The project is targeted for completion and full operation in August this year.

More from 20 May 2026 →

Cite this article