Presidential Staff Office conducts field verification to accelerate Palembang-Jambi Toll Road

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Presidential Staff Office conducts field verification to accelerate Palembang-Jambi Toll Road
Image: Antara (Indonesian)

The Presidential Staff Office (KSP) has carried out field verifications to accelerate the development of the National Strategic Project (PSN) for the Trans-Sumatra Toll Road, specifically the Palembang-Betung and Betung-Tempino-Jambi sections, near the Musi V Bridge in South Sumatra.

“KSP will record and report specifically to the Chief of Staff regarding the progress of construction as well as the obstacles still faced in the implementation of this project,” stated the Acting Deputy IV of KSS, Fadjar Dwi Wishnuwardhani, in a statement in Jakarta on Saturday. According to Fadjar, this direct inspection was conducted on Thursday (21/5) to ensure that various field constraints can be immediately coordinated and resolved through collective solutions. This step is intended to ensure that the construction of the Palembang–Betung–Tempino–Jambi section proceeds optimally and provides widespread benefits to the public.

This field verification activity is a follow-up to the Coordination Meeting for the Acceleration of the JTTS PSN Betung-Tempino-Jambi section held previously on 5 May 2026. Monitoring is being conducted to ensure all commitments to problem-solving proceed according to the agreed deadlines.

The Palembang-Betung section, spanning 69.19 km, represents an investment value of Rp14.981 trillion, with land acquisition progress reaching 76.40 per cent and construction at 65.98 per cent as of 15 May 2026. Meanwhile, the Betung-Tempino-Jambi section, spanning 170.73 km, has an investment value of Rp21.012 trillion, with land progress at 65.98 per cent and construction at 60.16 per cent.

Based on the verification results, KSP identified technical obstacles in land procurement within former forest areas and the need for confirmation letters regarding land plots affected by river basins (DAS). Other administrative hurdles include land asset releases and the failure to issue approvals for several land plots, which is hindering the consignment process. KSP noted that while some issues have been addressed according to the timeline, land acquisition issues still require acceleration. Consequently, KSP has reminded the Land Offices in the affected areas to immediately resolve these administrative obstacles.

Moving forward, KSP is committed to continuous verification and periodic monitoring of the acceleration of the Trans-Sumatra Toll Road National Strategic Project (PSN JTTS). The office stands ready to conduct further coordination meetings should any further obstacles be found in the field resolution process. The field verification agenda was also attended by representatives from the Ministry of Public Works, the Ministry of Agrarian Affairs and Spatial Planning/National Land Agency (ATR/BPN), and PT Hutama Karya (Persero) Tbk.

More from 23 May 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/presidential-staff-office-conducts-field-verification-to-accelerate-palembang-jambi-toll-road-1780883910)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5579985/ksp-verifikasi-lapangan-percepatan-tol-palembang-jambi), translated from Indonesian
Print