President Receives Task Force Report on 41 Subsequent Disasters in Sumatra
Jakarta (ANTARA) - President Prabowo Subianto received a progress report on the first year of post-disaster recovery in Sumatra from the Task Force for the Acceleration of Rehabilitation and Reconstruction (PRR).
The report was intended to support preparations, as areas affected in Aceh, North Sumatra and West Sumatra have been hit by 41 subsequent disasters.
“From April to October, I recorded 41 subsequent floods,” Home Affairs Minister and head of the Sumatra Post-Disaster PRR Task Force Tito Karnavian said after a limited meeting at the Presidential Palace in Jakarta on Monday.
The subsequent floods and landslides occurred most frequently in Aceh, with 18 incidents, followed by West Sumatra with 15 and North Sumatra with at least eight.
Tito said eastern Sumatra was experiencing drought, while the west, particularly the north, continued to receive heavy rain.
He said the President wanted an update at the meeting on the response one year after the disaster at the end of November 2025. The President also requested preventive measures, as rainfall in the affected areas is expected to remain high.
Tito said the disaster response had been divided into three stages. The emergency response period ran from November to the end of January, with the aim of saving residents. The transition period, from January to April, focused on restoring basic services, including roads.
The accelerated rehabilitation and reconstruction phase is scheduled to run for three years, from April 2026 to December 2028.
The recovery plan spans three years because the November 2025 disaster affected 53 regencies and cities and 4,533 villages, and displaced more than 2.1 million people.
“Personally, to be honest, based on what I have experienced, this is one of the most extensive impacts,” Tito said.
Rehabilitation and reconstruction are guided by the 2026–2028 Master Plan, which has been approved by the President. It comprises 11,520 activities with a total budget of Rp100.67 trillion: Rp100.1 trillion for 23 principal implementing ministries and agencies, and Rp575 billion for 10 supporting ministries and agencies.
Tito reported that provincial, regency and city, and sub-district administrations across the three provinces were now operating at full capacity. Aceh Tamiang had been among the worst-affected areas, as its regency administration had been completely unable to function.
Some village and urban-ward administrations are still being restored.
In the health sector, all 87 affected hospitals and 867 community health centres (puskesmas) have resumed operations. In North Sumatra, six auxiliary community health centres remain closed because landslides have blocked access roads.
The President then instructed the head of the National Disaster Mitigation Agency (BNPB) to prepare equipment. The defence minister, the Indonesian Military (TNI) commander and the National Police chief were told to remain on alert while monitoring weather forecasts from the Meteorology, Climatology and Geophysics Agency (BMKG). The government will also conduct weather modification operations in the affected areas.
The meeting was attended by Coordinating Minister for Human Development and Culture Sugiono, who chairs the task force’s steering team, as well as the defence minister, the National Police chief, the TNI commander, the public works minister, and the heads of BMKG and BNPB.
Source: jawawa.id (https://jawawa.id/newsitem/president-receives-task-force-report-on-41-subsequent-disasters-in-sumatra-1794236058)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5842515/presiden-terima-laporan-satgas-prr-soal-41-bencana-susulan-di-sumatera), translated from Indonesian