Pramono Inspects LRT Construction, Waskita Karya Guarantees On-Time Completion

| | Source: Republika Translated from Indonesian | Infrastructure
Pramono Inspects LRT Construction, Waskita Karya Guarantees On-Time Completion
Image: Republika

Jakarta Governor Pramono Anung, accompanied by Jakarta Propertindo (Jakpro) Chief Executive Iwan Takwin and Jakpro’s Director of Engineering and Development Robert Sajaka, made a direct inspection of the Jakarta LRT Phase 1B construction site on Tuesday (14 July 2026) to ensure the works proceed smoothly. Also present were PT LRT Jakarta Chief Executive Aditia Kesuma Negara and Waskita Karya’s Operations Director II Paulus Budi Kartiko.

During the visit, Pramono said the Jakarta LRT Phase 1B would serve as an inspiration and role model for solving Jakarta’s transport problems. He therefore thanked the contractors, Jakpro officials and LRT Jakarta personnel working on the Rp 4.1 trillion project.

“All of this work is being carried out entirely by the nation’s own children through PT Waskita and Nindya,” he said, as quoted from a press statement on Tuesday (14 July 2026).

Pramono hopes the Jakarta LRT Phase 1B can be inaugurated in August and become the new face of transport in the capital.

The Jakarta Provincial Government and Jakpro strongly support the Velodrome-Manggarai LRT route. In line with Governor Pramono’s hopes, Waskita Karya has assured that Jakarta will soon have a new public transport option that will support urban connectivity.

The infrastructure will link East Jakarta with Central Jakarta while strengthening intermodal integration at Manggarai Station.

“The steel box girder installation over the active Double-Double Track (DDT) Manggarai railway lines has now been completed, within a limited window time of less than three hours. The girder installation was carried out without disrupting the operations of commuter trains or intercity trains passing through the line,” Paulus explained in an official statement on Tuesday (14 July 2026).

This step demonstrates Waskita’s strong commitment to implementing the Quality, Health, Safety, and Environment (QHSE) system. Even as the project is accelerated, the company continues to observe quality standards and worker safety while minimising negative environmental impacts.

Indeed, Waskita has recorded an achievement of 7.5 million safe working hours without lost-time injuries in the Jakarta LRT Phase 1B construction. This achievement stands as proof of the consistent implementation of Occupational Safety and Health (K3) standards.

“These 7.5 million safe working hours form an important foundation for a project being executed amid Jakarta’s heavy traffic and limited working space. As is known, the main challenge (urban constraint) in the Jakarta LRT works includes Jakarta’s perpetually congested traffic,” he explained.

Paulus said the Jakarta LRT Phase 1B works have now entered the slab deck casting process, or structural flooring, on the bridge. This will be followed by the installation of precast parapet concrete and uditch drainage elements.

“The slab track casting is scheduled to be completed on 1 August. This will support preparations for train run testing all the way to Manggarai Station,” he said.

Paulus noted that train runs have already been conducted several times up to Kayu Manis Station. Testing of the 3.6-kilometre route has shown that the transport system is safe for public use.

“Systematic and structured testing of all components continues, from the track, signalling, electricity and communications, through to operational integration. Every metre of the Jakarta LRT Phase 1B route is part of Waskita’s responsibility to the public. That is why we carry out the work with full calculation, precision and constant coordination with Jakpro as the owner,” he said.

He continued that Waskita Karya’s involvement in the project is not merely about construction work, but also an opportunity to showcase its capabilities. This highly visible project means the quality of the work has a direct impact on the company’s long-term reputation.

Waskita Karya, he affirmed, is committed to continuing to support and safeguard the realisation of integrated transport in the capital as a whole. The Jakarta LRT construction also strengthens the company’s track record as a highly competitive state-owned construction firm, both domestically and abroad.

“We are optimistic that the presence of Jakarta LRT Phase 1B will not only add a modern public transport option, but also make residents’ mobility easier and encourage a shift from private vehicles to public transport. Ultimately, this will have a positive impact on the environment by supporting the government’s Net Zero Emission (NZE) target,” he said.

More from 14 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pramono-inspects-lrt-construction-waskita-karya-guarantees-on-time-completion-1784040804)
Originally published by Republika (https://ekonomi.republika.co.id/berita/ti62ws490/pramono-cek-pembangunan-lrt-waskita-karya-jamin-penyelesaian-proyek-tepat-waktu), translated from Indonesian
Print