Prabowo Warns Japan Over 28-Year Delay to Major Gas Project
Jakarta, CNBC Indonesia — President Prabowo Subianto said he had previously warned the Japanese government about a gas project run by a Japanese company in Indonesia’s Tanimbar Islands, Maluku, which had been stalled for 28 years.
Prabowo said he would not hesitate to revoke the contract if the company did not resume the project promptly.
The project he was referring to is the Masela gas block in Maluku, operated by Inpex Masela Ltd.
“I instructed the Energy and Mineral Resources Minister: if there is no real activity for more than two years, revoke it. There is a 28-year concession in Maluku, Southwest Maluku, Masela, in Tanimbar. It has not been worked on for 28 years. I flew to Japan and met a prominent figure there. I asked respectfully and politely: ‘Your Excellency, is Japan, is Inpex, still interested in working on it? If not, we will have to revoke it because our people need it very much; many are still living in hardship.’ God willing, they attended yesterday and promised that activities would begin within six months. We shall see,” Prabowo said at the 2026 National Coordination Meeting of the Regional Financial Access Acceleration Team (TPAKD) at the JIEXPO Convention Centre on Thursday (22 October 2026).
“We respect everyone. I have said many times that Indonesians are courteous and welcoming, and like to receive guests. That is our nature. But sometimes our hospitality and kindness can make us naïve. Naïveté can be seen as innocence, and in a competitive world it can sometimes be taken for stupidity,” he said.
“We must therefore be careful. Javanese leadership philosophy teaches that a leader must not be naïve; I think all ethnic groups teach that a leader must not be naïve, but must be vigilant. In Javanese philosophy, it is ‘eling lan waspada’ — remember and stay alert. People may misunderstand vigilance as paranoia, but sometimes paranoia is necessary. Fire is dangerous if you are not careful: we need it, but it can also harm us,” he added.
Masela Block groundbreaking
After 28 years of delays, President Prabowo officiated the groundbreaking of the giant Abadi Field gas project in the Masela Block, in the Tanimbar Islands, Maluku, on Thursday (16 July 2026).
Prabowo presided by video conference from the State Palace in Jakarta. Officials attending in person in the Tanimbar Islands included Energy and Mineral Resources Minister Bahlil Lahadalia, Agrarian Affairs and Spatial Planning Minister Nusron Wahid, Presidential Chief of Staff Dudung Abdurachman, SKK Migas head Djoko Siswanto and Tanimbar Islands Regent Ricky Jauwerissa.
The event was also attended by Inpex Corporation chief executive Takayuki Ueda. Inpex is the operator and majority owner of the Masela Block, with a 65% participating interest (PI).
Prabowo said the government was grateful that construction of the National Strategic Project (PSN) had finally begun after nearly three decades of waiting.
“The development of a nation is the result of hard work and a long journey requiring unity among all parties and elements. The Abadi Masela national strategic project is therefore extremely important,” he said at the ceremony by video link from Jakarta on Thursday (16 July 2026).
“We have waited almost three decades. The people have waited for three decades. Thank God, today construction is beginning, and it must not be delayed; it must be completed as quickly as possible,” he said.
“From the outset, we have understood and consistently emphasised that the purpose of a nation’s independence is, first of all, to ensure its survival. In the modern world — as has been the case for hundreds or even thousands of years — energy is one of the conditions for a nation’s survival. Indonesia knows it has been blessed abundantly by God,” he said.
“One example is that we know there are very large energy reserves in our waters off Tanimbar, in Maluku. We have known this for 28 years, and we appreciate and recognise everyone who has helped make this project possible,” he added.
“We appreciate our Japanese partners who are investing here, and Inpex. We thank our Malaysian partners at Petronas for joining us, and we are proud that our national company Pertamina is involved. We must all work together so that the project succeeds, comes on stream quickly and begins generating returns,” Prabowo said.
“Today we can take heart and be proud. After decades, the project is beginning, and we value our Japanese partners. We are seeking mutual benefit; a host’s honour lies in the happiness of its partners and guests,” he said.
“The project is important, and I welcome its start. As mentioned earlier, it represents a major investment of US$20.9 billion, almost US$21 billion, and will produce more than nine million tonnes of gas condensate and other products, helping Indonesia carry out its development,” he added.
About the Masela Block
The project, with an investment value of US$20.95 billion, has estimated gas resources of 6.97 trillion cubic feet (TCF).
Gas from the Masela Block will be processed into liquefied natural gas (LNG) at an onshore plant with capacity of 9.5 million tonnes per year (MTPA). The block is also expected to produce 150 million standard cubic feet per day (MMSCFD) of pipeline gas and 35,000 barrels per day (bpd) of condensate.
Indonesians have been waiting a long time for the project. Inpex Corporation, the block’s operator, signed the Masela production-sharing contract (PSC) with the Indonesian government on 16 November 1998, during President B.J. Habibie’s administration.
Nearly 30 years after the contract was signed, the project has yet to operate or produce oil and gas for Indonesia.
The Masela PSC was extended for 20 years, with a further seven-year extension, through to 2055. The extension to Inpex’s production-sharing contract was signed in October 2017, when Ignasius Jonan was Energy and Mineral Resources Minister. Inpex’s original contract was due to expire in 2028, after a 30-year term with the Indonesian government.
As the project had not begun operating and Inpex had committed to continuing it, the Indonesian government granted an extension of 20 years from 2028, plus an additional seven years after changing the LNG plant’s planned location from offshore to onshore.
Inpex Masela Ltd holds the largest participating interest in the Masela Block, at 65%.
Inpex was previously partnered by Shell Upstream Overseas Services, which held 35%. Shell later decided to withdraw from the Maluku gas project.
Since July 2023, Shell’s 35% interest has been taken up by Pertamina Hulu Energi, through its subsidiary PT Pertamina Hulu Energi Masela (PHE Masela), which acquired 20%, and Petronas, which acquired 15%.
The sale and purchase agreement transferring the participating interest from Shell to Pertamina and Petronas was signed on 25 July 2023. The Energy and Mineral Resources Minister approved the transfer on 4 October 2023.
Abadi Field in the Masela Block is a deep-water gas field with Indonesia’s largest gas reserves. It is located about 160 kilometres off Yamdena Island in the Arafura Sea, at a water depth of 400–800 metres. Its estimated gas resources amount to 6.97 trillion cubic feet (TCF).
After the production-sharing contract was signed in 1998, Inpex discovered the major gas reserves in the Masela Block in 2000.
Nineteen years later, the Indonesian government approved Inpex’s first Plan of Development (PoD-I), which set out production of 9.5 million tonnes of LNG a year (MTPA), 150 million standard cubic feet per day (MMSCFD) of pipeline gas and 35,000 barrels per day (bpd) of condensate.
Developing this complex, high-risk greenfield oil and gas project will involve deep-water drilling, subsea facilities, a floating production, storage and offloading (FPSO) vessel, and an onshore LNG plant. It will be a major challenge and opportunity for PHE and its partners, and could create up to 10,000 jobs.
The Masela Block is also planned to produce cleaner energy through carbon capture and storage (CCS), supporting the government’s efforts to reduce carbon emissions and advance sustainability during the energy transition.
The Indonesian government approved the CCS plan on 28 November 2023 through Revision 2 of the Plan of Development-I. A front-end engineering design (FEED) tender followed, and on Wednesday, 9 April 2025, Inpex launched the FEED for the onshore LNG project.