Power Crisis Looms for Gas-Short Central Java
The Jakarta Globe
By Euis Erita Hartati
Technicians check electricity meters at a budget apartment complex in East Jakarta on September 30. Government officials have warned that Yogyakarta and Central Java risk electricity shortages in 2016 should uncertainty surrounding gas pipeline projects worth hundreds of million of dollars not be resolved soon..(JG Photo/Safir Makki)
Yogyakarta and Central Java risk electricity shortages in 2016 should uncertainty surrounding gas pipeline projects worth hundreds of million of dollars not be resolved soon, government officials have warned.
Supriyono, a spokesman for the Central Java and Yogyakarta office of state power company Perusahaan Listrik Negara, said over the weekend that the peak load of electricity usage in the two provinces currently stood at 3.2 gigawatts (GW).
However, PLN’s grid in the two provinces can only supply a maximum of 2.5 GW he said, adding that Central Java currently relied on supplies from neighboring provinces East Java and West Java to make up the shortfall.
Teguh Dwi Paryono, the head of the East Java Energy and Mineral Resources Office, called on Pertagas, a subsidiary of state-owned energy company Pertamina, to confirm its commitment to developing a 267-kilometer gas pipeline from Gresik in East Java to Semarang, the Central Java capital.
The project is vital for reviving PLN’s gas-fired Tambak Lorok plant in Semarang, which was shut down two years ago due to a fuel supply shortage.
The government earlier ordered PLN to shut down the 500-megawatt (MW) plant, which can run on either natural gas or diesel , in order to avoid soaring costs related to the use of diesel.
“Should there be no certainty over the gas supply, Central Java could experience a power crisis by 2016,” Teguh said.
Gunung Sardjono Hadi, president director of Pertagas, whose business includes the transmission and distribution of natural gas, told reporters in March that the company expected to start working on the gas pipeline by the middle of this year and that it was expected to be completed by the end of next year.
But to date, work on the pipeline, with an estimated cost of $500 million and a designed carrying capacity of up to 500 million standard cubic feet of gas per day, has not yet commenced.
Teguh said two new cement factories in Rembang and Banyumas districts would need an additional 70 MW of electricity once they started operations next year.
He added that Central Java could not continue to rely on supply from other provinces, as those provinces are also experiencing economic growth, which would also boost demand for electricity.
Meanwhile, Pertagas corporate secretary Eko Agus said one of the problems facing the company was uncertainty over securing gas supplies.
He said that Pertagas had been expecting to secure gas supplies from the Madura Strait offshore block, operated by Canadian firm Husky Energy.
Gas pipelines are currently in the spotlight in Indonesia, due to controversy over the implementation of the so-called “open access” policy, which would allow anyone to deliver and distribute natural gas through the pipeline network of gas distributors, especially Pertagas and state-owned Perusahaan Gas Negara.
PGN has resisted the scheme, saying it would cost billions of dollars in infrastructure upgrades, while it also blamed other gas distributors, such as Pertagas, for being slow in developing gas infrastructure.
Source: jawawa.id (https://jawawa.id/newsitem/power-crisis-looms-for-gas-short-central-java-1383498000)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/news/power-crisis-looms-for-gas-short-central-java/)