Indonesian Political, Business & Finance News

PLN's Coal Supply Dwindles Faster Than Expected, Bahlil Suspects Something Amiss

| Source: detikBali Translated from Indonesian | Energy
PLN's Coal Supply Dwindles Faster Than Expected, Bahlil Suspects Something Amiss
Image: detikBali

The Minister of Energy and Mineral Resources, Bahlil Lahadalia, has evaluated the performance of PT PLN (Persero) following recent rolling blackouts on Java Island. The evaluation involved investigating various factors affecting the stability of the national electricity supply.

According to reports, Bahlil explained that the total coal requirement for PLN’s power plants over a year is approximately 154 million metric tons. Based on the Domestic Market Obligation (DMO) regulations for exporters, PLN is entitled to a supply of up to 180-190 million metric tons.

Of this total requirement, Bahlil stated that 141 million metric tons of coal have been received by PLN. The remainder will be fulfilled gradually alongside ongoing coal export activities.

“They have expressed their willingness to provide 160 million to 170 million (metric) tons. Of the amount already contracted by PLN, 134 million metric tons were covered. As of three days ago, it has reached 141 million metric tons,” Bahlil said during the CNBC Energy Forum 2026 in Central Jakarta on Thursday (25/06/2026).

Bahlil noted that coal supplies for electricity production began to thin in June 2026, a situation that prompted his questioning.

“This means from 1 January until June, from 154 million minus 141 million, that leaves only 13 million. How can coal run out in June? What kind of logic is this? To be honest, this implies something is wrong,” he remarked.

Upon investigation, Bahlil discovered that the issue lies in the quality of the coal received by PLN, which falls below the required standard. Consequently, a larger volume of coal is needed to generate the same amount of electricity.

He argued that this issue should have been mitigated by PLN well in advance, rather than waiting until a crisis occurs to report and complain.

“We checked and found medium-grade coal with a calorific value above 5,000 is needed for blending. This is what is required. If the government provides the DMO, the technical execution lies with you, PLN. Do not wait until the water is at your throat before you scream. That is why for the past two weeks, I have acted as a project manager for PLN,” Bahlil concluded.

More from 26 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/plns-coal-supply-dwindles-faster-than-expected-bahlil-suspects-something-amiss-1782438648)
Originally published by detikBali (https://www.detik.com/bali/berita/d-8547815/pasokan-batu-bara-pln-menipis-lebih-cepat-bahlil-berarti-ada-sesuatu), translated from Indonesian
Print